Collective construction progress

The register lists Collective in Dubai Hills Estate as complete, with a registered completion date of March 2022. Its last site inspection on record was in January 2022. The developer is Dubai Hills Estate.

100%

Built, at the site inspection of 12 January 2022

Construction complete

Registered completion date
March 2022
Construction started
September 2018
First registered
April 2018
Units
477
Escrow bank
Dubai Islamic Bank
Name in Arabic
كولكتيف
Project number
2047
Site inspections
11

Schedule

The register lists Collective as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2019202020212022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 January 2022

100%+1.9 pts

  • Collective construction site, inspection photo 1, 12 January 2022
  • Collective construction site, inspection photo 2, 12 January 2022
  • Collective construction site, inspection photo 3, 12 January 2022
  • Collective construction site, inspection photo 4, 12 January 2022

21 November 2021

98%+7.3 pts

  • Collective construction site, inspection photo 1, 21 November 2021
  • Collective construction site, inspection photo 2, 21 November 2021
  • Collective construction site, inspection photo 3, 21 November 2021
  • Collective construction site, inspection photo 4, 21 November 2021

10 August 2021

91%+10 pts

  • Collective construction site, inspection photo 1, 10 August 2021
  • Collective construction site, inspection photo 2, 10 August 2021
  • Collective construction site, inspection photo 3, 10 August 2021
  • Collective construction site, inspection photo 4, 10 August 2021

5 May 2021

81%+21 pts

  • Collective construction site, inspection photo 1, 5 May 2021
  • Collective construction site, inspection photo 2, 5 May 2021
  • Collective construction site, inspection photo 3, 5 May 2021
  • Collective construction site, inspection photo 4, 5 May 2021

20 January 2021

60%+19 pts

  • Collective construction site, inspection photo 1, 20 January 2021
  • Collective construction site, inspection photo 2, 20 January 2021
  • Collective construction site, inspection photo 3, 20 January 2021
  • Collective construction site, inspection photo 4, 20 January 2021

12 October 2020

41%+8.0 pts

  • Collective construction site, inspection photo 1, 12 October 2020
  • Collective construction site, inspection photo 2, 12 October 2020
  • Collective construction site, inspection photo 3, 12 October 2020
  • Collective construction site, inspection photo 4, 12 October 2020

20 July 2020

33%+25 pts

  • Collective construction site, inspection photo 1, 20 July 2020
  • Collective construction site, inspection photo 2, 20 July 2020
  • Collective construction site, inspection photo 3, 20 July 2020
  • Collective construction site, inspection photo 4, 20 July 2020

13 October 2019

7.8%+4.0 pts

  • Collective construction site, inspection photo 1, 13 October 2019
  • Collective construction site, inspection photo 2, 13 October 2019
  • Collective construction site, inspection photo 3, 13 October 2019
  • Collective construction site, inspection photo 4, 13 October 2019

10 July 2019

3.8%+3.7 pts

  • Collective construction site, inspection photo 1, 10 July 2019
  • Collective construction site, inspection photo 2, 10 July 2019
  • Collective construction site, inspection photo 3, 10 July 2019
  • Collective construction site, inspection photo 4, 10 July 2019

19 March 2019

0.1%+0.1 pts

  • Collective construction site, inspection photo 1, 19 March 2019
  • Collective construction site, inspection photo 2, 19 March 2019
  • Collective construction site, inspection photo 3, 19 March 2019
  • Collective construction site, inspection photo 4, 19 March 2019

All 106 site photos, by inspection date

Context

Dubai Hills Estate has 19 projects under construction, 44% built on average.

Dubai Hills Estate has 18 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Collective?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Collective handover date?
Construction of Collective is recorded as complete, with a registered completion date of March 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Collective?
Collective was 100% built at the site inspection on 12 January 2022. The site has been inspected 11 times since November 2018. The Land Department took 106 site photos at its inspections.
Is Collective delayed?
The register lists construction as complete.
Who is building Collective?
The registered developer is Dubai Hills Estate. It has 18 other projects under construction in Dubai.
Which bank holds the escrow account for Collective?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.