Collective construction photos

106 photos from 11 site inspections, newest first. The percentage is how much of Collective was built on the day of each visit.

12 January 2022100% built

21 November 202198% built

10 August 202191% built

5 May 202181% built

20 January 202160% built

12 October 202041% built

20 July 202033% built

13 October 20197.8% built

10 July 20193.8% built

19 March 20190.1% built

1 November 20180% built

Back to Collective construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.