Armani Beach Residences At Palm Jumeirah construction progress
The registered completion date for Armani Beach Residences At Palm Jumeirah in Palm Jumeirah is December 2027. At the last site inspection, in July 2026, it was 10% built. The developer is Arada Developments S.o.c.
10%
Built, at the site inspection of 20 July 2026
Running behind its date
- Registered completion date
- December 2027
- Finish at recent pace
- April 2041
- Construction started
- June 2024
- First registered
- January 2024
- Developer
- Arada Developments S.o.c
- Community
- Palm Jumeirah
- Units
- 57
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- أرماني بيتش رزيدنسز في نخلة جميرا
- Project number
- 2889
- Site inspections
- 7
Schedule
Between November 2025 and July 2026 the site added about 0.5 points a month. At that rate it would finish around April 2041, more than three months after its registered date of December 2027.
Site inspections
20 July 2026
10%+2.9 pts
4 March 2026
7.2%+1.3 pts
6 November 2025
5.9%+2.4 pts
24 June 2025
3.5%+1.1 pts
25 February 2025
2.4%+2.2 pts
16 October 2024
0.2%+0.2 pts
18 December 2023
0%
Context
Palm Jumeirah has 16 projects under construction, 45% built on average.
Arada Developments S.o.c has 5 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Armani Beach Residences At Palm Jumeirah?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Armani Beach Residences At Palm Jumeirah handover date?
- The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2041. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Armani Beach Residences At Palm Jumeirah?
- Armani Beach Residences At Palm Jumeirah was 10% built at the site inspection on 20 July 2026. The site has been inspected 7 times since December 2023. The Land Department took 35 site photos at its inspections.
- Is Armani Beach Residences At Palm Jumeirah delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building Armani Beach Residences At Palm Jumeirah?
- The registered developer is Arada Developments S.o.c. It has 4 other projects under construction in Dubai.
- Which bank holds the escrow account for Armani Beach Residences At Palm Jumeirah?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Jouri HillsAlso by Arada Developments S.o.c. 78%, Due June 2026, passed.
- W Residences At Dubai HarbourAlso by Arada Developments S.o.c. 4.0%, Due December 2028.
- Akala Hotels And ResidencesAlso by Arada Developments S.o.c. 1.9%, Due October 2029.
- Inaura Hotels & ResidencesAlso by Arada Developments S.o.c. 1.3%, Due June 2030.
- Palm Beach Towers -1Nearby in Palm Jumeirah. 83%, Due December 2026.
- Palm Beach Towers - 2Nearby in Palm Jumeirah. 82%, Due December 2026.
- Palm Beach Towers -3Nearby in Palm Jumeirah. 74%, Due December 2026.
- Orla By OmniyatNearby in Palm Jumeirah. 70%, Due December 2026.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.















.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)