Jouri Hills construction progress

Jouri Hills in Jumeirah Golf Estates was registered to complete in June 2026 and is still under construction. At the last site inspection, in October 2026, it was 78% built. The developer is Arada Developments S.o.c.

78%

Built, at the site inspection of 5 October 2026

5 months past its registered completion date

Registered completion date
June 2026
Finish at recent pace
March 2027
Construction started
August 2023
First registered
November 2022
Units
295
Escrow bank
Dubai Islamic Bank
Name in Arabic
جوري هيلز
Project number
2506
Site inspections
10

Schedule

Jouri Hills was registered to complete in June 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 4.0 points a month. Kept at that rate, the site would reach 100% around March 2027.

0%25%50%75%100%2023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 October 2026

78%+20 pts

  • Jouri Hills construction site, inspection photo 1, 5 October 2026
  • Jouri Hills construction site, inspection photo 2, 5 October 2026
  • Jouri Hills construction site, inspection photo 3, 5 October 2026
  • Jouri Hills construction site, inspection photo 4, 5 October 2026

23 April 2026

58%+6.2 pts

  • Jouri Hills construction site, inspection photo 1, 23 April 2026
  • Jouri Hills construction site, inspection photo 2, 23 April 2026
  • Jouri Hills construction site, inspection photo 3, 23 April 2026
  • Jouri Hills construction site, inspection photo 4, 23 April 2026

16 March 2026

52%+20 pts

  • Jouri Hills construction site, inspection photo 1, 16 March 2026
  • Jouri Hills construction site, inspection photo 2, 16 March 2026
  • Jouri Hills construction site, inspection photo 3, 16 March 2026
  • Jouri Hills construction site, inspection photo 4, 16 March 2026

14 October 2025

32%+12 pts

  • Jouri Hills construction site, inspection photo 1, 14 October 2025
  • Jouri Hills construction site, inspection photo 2, 14 October 2025
  • Jouri Hills construction site, inspection photo 3, 14 October 2025
  • Jouri Hills construction site, inspection photo 4, 14 October 2025

9 July 2025

20%+8.0 pts

  • Jouri Hills construction site, inspection photo 1, 9 July 2025
  • Jouri Hills construction site, inspection photo 2, 9 July 2025
  • Jouri Hills construction site, inspection photo 3, 9 July 2025
  • Jouri Hills construction site, inspection photo 4, 9 July 2025

5 March 2025

12%+7.1 pts

  • Jouri Hills construction site, inspection photo 1, 5 March 2025
  • Jouri Hills construction site, inspection photo 2, 5 March 2025
  • Jouri Hills construction site, inspection photo 3, 5 March 2025
  • Jouri Hills construction site, inspection photo 4, 5 March 2025

29 August 2024

4.8%+2.7 pts

  • Jouri Hills construction site, inspection photo 1, 29 August 2024
  • Jouri Hills construction site, inspection photo 2, 29 August 2024
  • Jouri Hills construction site, inspection photo 3, 29 August 2024

13 March 2024

2.0%+2.0 pts

  • Jouri Hills construction site, inspection photo 1, 13 March 2024
  • Jouri Hills construction site, inspection photo 2, 13 March 2024
  • Jouri Hills construction site, inspection photo 3, 13 March 2024
  • Jouri Hills construction site, inspection photo 4, 13 March 2024

21 August 2023

0%

  • Jouri Hills construction site, inspection photo 1, 21 August 2023
  • Jouri Hills construction site, inspection photo 2, 21 August 2023

10 November 2022

0%

  • Jouri Hills construction site, inspection photo 1, 10 November 2022
  • Jouri Hills construction site, inspection photo 2, 10 November 2022

All 72 site photos, by inspection date

Context

Jumeirah Golf Estates has 4 projects under construction, 49% built on average.

Arada Developments S.o.c has 5 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Jouri Hills?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Jouri Hills handover date?
The registered completion date was June 2026, and the register still lists Jouri Hills as under construction. At the pace of its recent inspections the site would reach 100% around March 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Jouri Hills?
Jouri Hills was 78% built at the site inspection on 5 October 2026. The site has been inspected 10 times since November 2022. The Land Department took 72 site photos at its inspections.
Is Jouri Hills delayed?
Yes. Its registered completion date of June 2026 has passed and the project is still listed as under construction.
Who is building Jouri Hills?
The registered developer is Arada Developments S.o.c. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Jouri Hills?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.