Vida Dubai Mall construction progress

The register lists Vida Dubai Mall in DownTown Dubai as complete, with a registered completion date of December 2022. Its last site inspection on record was in February 2025. The developer is Emaar Development.

100%

Built, at the site inspection of 17 February 2025

Construction complete

Registered completion date
December 2022
Construction started
October 2017
First registered
April 2017
Units
682
Escrow bank
First Abu Dhabi Bank
Name in Arabic
فيدا دبي مول
Project number
1898
Site inspections
20

Schedule

The register lists Vida Dubai Mall as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2018202020222024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 February 2025

100%+2.4 pts

  • Vida Dubai Mall construction site, inspection photo 1, 17 February 2025
  • Vida Dubai Mall construction site, inspection photo 2, 17 February 2025
  • Vida Dubai Mall construction site, inspection photo 3, 17 February 2025
  • Vida Dubai Mall construction site, inspection photo 4, 17 February 2025

6 May 2024

98%+5.0 pts

  • Vida Dubai Mall construction site, inspection photo 1, 6 May 2024
  • Vida Dubai Mall construction site, inspection photo 2, 6 May 2024
  • Vida Dubai Mall construction site, inspection photo 3, 6 May 2024
  • Vida Dubai Mall construction site, inspection photo 4, 6 May 2024

8 November 2023

93%+3.6 pts

  • Vida Dubai Mall construction site, inspection photo 1, 8 November 2023
  • Vida Dubai Mall construction site, inspection photo 2, 8 November 2023
  • Vida Dubai Mall construction site, inspection photo 3, 8 November 2023
  • Vida Dubai Mall construction site, inspection photo 4, 8 November 2023

24 July 2023

89%+3.0 pts

  • Vida Dubai Mall construction site, inspection photo 1, 24 July 2023
  • Vida Dubai Mall construction site, inspection photo 2, 24 July 2023
  • Vida Dubai Mall construction site, inspection photo 3, 24 July 2023
  • Vida Dubai Mall construction site, inspection photo 4, 24 July 2023

10 February 2023

86%+5.0 pts

  • Vida Dubai Mall construction site, inspection photo 1, 10 February 2023
  • Vida Dubai Mall construction site, inspection photo 2, 10 February 2023
  • Vida Dubai Mall construction site, inspection photo 3, 10 February 2023
  • Vida Dubai Mall construction site, inspection photo 4, 10 February 2023

14 September 2022

81%+10 pts

  • Vida Dubai Mall construction site, inspection photo 1, 14 September 2022
  • Vida Dubai Mall construction site, inspection photo 2, 14 September 2022
  • Vida Dubai Mall construction site, inspection photo 3, 14 September 2022
  • Vida Dubai Mall construction site, inspection photo 4, 14 September 2022

25 May 2022

71%+12 pts

  • Vida Dubai Mall construction site, inspection photo 1, 25 May 2022
  • Vida Dubai Mall construction site, inspection photo 2, 25 May 2022
  • Vida Dubai Mall construction site, inspection photo 3, 25 May 2022
  • Vida Dubai Mall construction site, inspection photo 4, 25 May 2022

27 October 2021

58%+5.6 pts

  • Vida Dubai Mall construction site, inspection photo 1, 27 October 2021
  • Vida Dubai Mall construction site, inspection photo 2, 27 October 2021
  • Vida Dubai Mall construction site, inspection photo 3, 27 October 2021
  • Vida Dubai Mall construction site, inspection photo 4, 27 October 2021

29 July 2021

53%+8.3 pts

  • Vida Dubai Mall construction site, inspection photo 1, 29 July 2021
  • Vida Dubai Mall construction site, inspection photo 2, 29 July 2021
  • Vida Dubai Mall construction site, inspection photo 3, 29 July 2021
  • Vida Dubai Mall construction site, inspection photo 4, 29 July 2021

7 April 2021

45%+11 pts

  • Vida Dubai Mall construction site, inspection photo 1, 7 April 2021
  • Vida Dubai Mall construction site, inspection photo 2, 7 April 2021
  • Vida Dubai Mall construction site, inspection photo 3, 7 April 2021
  • Vida Dubai Mall construction site, inspection photo 4, 7 April 2021

All 202 site photos, by inspection date

Context

DownTown Dubai has 13 projects under construction, 35% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Vida Dubai Mall?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Vida Dubai Mall handover date?
Construction of Vida Dubai Mall is recorded as complete, with a registered completion date of December 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Vida Dubai Mall?
Vida Dubai Mall was 100% built at the site inspection on 17 February 2025. The site has been inspected 20 times since January 2018. The Land Department took 202 site photos at its inspections.
Is Vida Dubai Mall delayed?
The register lists construction as complete.
Who is building Vida Dubai Mall?
The registered developer is Emaar Development. It has 52 other projects under construction in Dubai.
Which bank holds the escrow account for Vida Dubai Mall?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.