Vida Dubai Mall construction photos

202 photos from 20 site inspections, newest first. The percentage is how much of Vida Dubai Mall was built on the day of each visit.

17 February 2025100% built

6 May 202498% built

8 November 202393% built

24 July 202389% built

10 February 202386% built

14 September 202281% built

25 May 202271% built

27 October 202158% built

29 July 202153% built

7 April 202145% built

23 December 202034% built

9 September 202026% built

3 June 202022% built

13 February 202018% built

16 September 201912% built

8 May 20197.3% built

28 January 20196.9% built

30 August 20182.5% built

29 April 20180.2% built

21 January 20180% built

Back to Vida Dubai Mall construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.