94 photos from 14 site inspections, newest first. The percentage is how much of The St. Regis Residences, Downtown Dubai was built on the day of each visit.

2 June 202676% built

3 February 202666% built

1 October 202551% built

10 June 202540% built

29 January 202527% built

12 September 202420% built

6 May 202413% built

30 October 20239.2% built

4 July 20237.1% built

27 March 20235.5% built

20 December 20220.8% built

31 August 20220.6% built

6 January 20220% built

13 December 20210% built

Back to The St. Regis Residences, Downtown Dubai construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.