The Address Residence Fountain Views III construction progress
The register lists The Address Residence Fountain Views III in DownTown Dubai as complete, with a registered completion date of September 2019. Its last site inspection on record was in December 2019. The developer is Emaar Development.
100%
Built, at the site inspection of 10 December 2019
Construction complete
- Registered completion date
- September 2019
- Construction started
- May 2013
- First registered
- September 2013
- Developer
- Emaar Development
- Community
- DownTown Dubai
- Units
- 212
- Escrow bank
- Mashreq Bank
- Name in Arabic
- ذا أدريس ريزيدنس فاونتن فيوز Iii
- Project number
- 1372
- Site inspections
- 14
Schedule
The register lists The Address Residence Fountain Views III as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
10 December 2019
100%+2.7 pts
4 November 2019
97%+2.8 pts
15 July 2019
94%+2.0 pts
20 February 2019
92%+3.6 pts
29 October 2018
89%+4.6 pts
18 July 2018
84%+3.7 pts
3 April 2018
80%+7.2 pts
12 December 2017
73%+5.4 pts
8 August 2017
68%+16 pts
29 March 2017
52%+9.4 pts
Context
DownTown Dubai has 13 projects under construction, 35% built on average.
Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.
Own a unit in The Address Residence Fountain Views III?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the The Address Residence Fountain Views III handover date?
- Construction of The Address Residence Fountain Views III is recorded as complete, with a registered completion date of September 2019. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on The Address Residence Fountain Views III?
- The Address Residence Fountain Views III was 100% built at the site inspection on 10 December 2019. The site has been inspected 14 times since December 2014. The Land Department took 144 site photos at its inspections.
- Is The Address Residence Fountain Views III delayed?
- The register lists construction as complete.
- Who is building The Address Residence Fountain Views III?
- The registered developer is Emaar Development. It has 52 other projects under construction in Dubai.
- Which bank holds the escrow account for The Address Residence Fountain Views III?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The St. Regis Residences, Downtown DubaiAlso by Emaar Development. 76%, Due December 2026.
- Address The BayAlso by Emaar Development. 70%, Due December 2026.
- SeapointAlso by Emaar Development. 37%, Due March 2028.
- BayviewAlso by Emaar Development. 63%, Due July 2028.
- City Center ResidencesNearby in DownTown Dubai. 72%, Due September 2026, passed.
- Mercedes-Benz Places | BinghattiNearby in DownTown Dubai. 65%, Due December 2026.
- Baccarat Hotel And Residences, DubaiNearby in DownTown Dubai. 21%, Due December 2026.
- Rove Home Residences By IrthNearby in DownTown Dubai. 63%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.