The Address Residence Fountain Views III construction photos

144 photos from 14 site inspections, newest first. The percentage is how much of The Address Residence Fountain Views III was built on the day of each visit.

10 December 2019100% built

4 November 201997% built

15 July 201994% built

20 February 201992% built

29 October 201889% built

18 July 201884% built

3 April 201880% built

12 December 201773% built

8 August 201768% built

29 March 201752% built

15 December 201642% built

12 July 201635% built

31 August 201522% built

10 December 201412% built

Back to The Address Residence Fountain Views III construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.