Il Primo construction progress

The register lists Il Primo in DownTown Dubai as complete, with a registered completion date of December 2022. Its last site inspection on record was in August 2024. The developer is Emaar Development.

100%

Built, at the site inspection of 30 August 2024

Construction complete

Registered completion date
December 2022
Construction started
November 2016
First registered
May 2016
Units
137
Escrow bank
First Abu Dhabi Bank
Name in Arabic
Il بريمو
Project number
1757
Site inspections
21

Schedule

The register lists Il Primo as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2017201920212023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 August 2024

100%+4.6 pts

  • Il Primo construction site, inspection photo 1, 30 August 2024
  • Il Primo construction site, inspection photo 2, 30 August 2024
  • Il Primo construction site, inspection photo 3, 30 August 2024
  • Il Primo construction site, inspection photo 4, 30 August 2024

2 April 2024

95%+3.4 pts

  • Il Primo construction site, inspection photo 1, 2 April 2024
  • Il Primo construction site, inspection photo 2, 2 April 2024
  • Il Primo construction site, inspection photo 3, 2 April 2024
  • Il Primo construction site, inspection photo 4, 2 April 2024

21 August 2023

92%+2.0 pts

  • Il Primo construction site, inspection photo 1, 21 August 2023
  • Il Primo construction site, inspection photo 2, 21 August 2023
  • Il Primo construction site, inspection photo 3, 21 August 2023
  • Il Primo construction site, inspection photo 4, 21 August 2023

12 April 2023

90%+3.0 pts

  • Il Primo construction site, inspection photo 1, 12 April 2023
  • Il Primo construction site, inspection photo 2, 12 April 2023
  • Il Primo construction site, inspection photo 3, 12 April 2023
  • Il Primo construction site, inspection photo 4, 12 April 2023

29 December 2022

87%+3.0 pts

  • Il Primo construction site, inspection photo 1, 29 December 2022
  • Il Primo construction site, inspection photo 2, 29 December 2022
  • Il Primo construction site, inspection photo 3, 29 December 2022
  • Il Primo construction site, inspection photo 4, 29 December 2022

31 August 2022

84%+6.7 pts

  • Il Primo construction site, inspection photo 1, 31 August 2022
  • Il Primo construction site, inspection photo 2, 31 August 2022
  • Il Primo construction site, inspection photo 3, 31 August 2022
  • Il Primo construction site, inspection photo 4, 31 August 2022

11 May 2022

77%+7.2 pts

  • Il Primo construction site, inspection photo 1, 11 May 2022
  • Il Primo construction site, inspection photo 2, 11 May 2022
  • Il Primo construction site, inspection photo 3, 11 May 2022
  • Il Primo construction site, inspection photo 4, 11 May 2022

9 November 2021

70%+5.0 pts

  • Il Primo construction site, inspection photo 1, 9 November 2021
  • Il Primo construction site, inspection photo 2, 9 November 2021
  • Il Primo construction site, inspection photo 3, 9 November 2021
  • Il Primo construction site, inspection photo 4, 9 November 2021

28 July 2021

65%+5.1 pts

  • Il Primo construction site, inspection photo 1, 28 July 2021
  • Il Primo construction site, inspection photo 2, 28 July 2021
  • Il Primo construction site, inspection photo 3, 28 July 2021
  • Il Primo construction site, inspection photo 4, 28 July 2021

31 March 2021

60%+10.0 pts

  • Il Primo construction site, inspection photo 1, 31 March 2021
  • Il Primo construction site, inspection photo 2, 31 March 2021
  • Il Primo construction site, inspection photo 3, 31 March 2021
  • Il Primo construction site, inspection photo 4, 31 March 2021

All 186 site photos, by inspection date

Context

DownTown Dubai has 13 projects under construction, 35% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Il Primo?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Il Primo handover date?
Construction of Il Primo is recorded as complete, with a registered completion date of December 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Il Primo?
Il Primo was 100% built at the site inspection on 30 August 2024. The site has been inspected 21 times since January 2017. The Land Department took 186 site photos at its inspections.
Is Il Primo delayed?
The register lists construction as complete.
Who is building Il Primo?
The registered developer is Emaar Development. It has 52 other projects under construction in Dubai.
Which bank holds the escrow account for Il Primo?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.