Il Primo construction photos

186 photos from 21 site inspections, newest first. The percentage is how much of Il Primo was built on the day of each visit.

30 August 2024100% built

2 April 202495% built

21 August 202392% built

12 April 202390% built

29 December 202287% built

31 August 202284% built

11 May 202277% built

9 November 202170% built

28 July 202165% built

31 March 202160% built

14 April 202050% built

8 January 202040% built

27 August 201928% built

5 May 201921% built

15 January 201917% built

26 September 201813% built

28 May 201810% built

6 February 20187.3% built

6 September 20175.1% built

11 May 20173.3% built

9 January 20171.1% built

Back to Il Primo construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.