Skip to content

Boulevard Point construction progress

The register lists Boulevard Point in DownTown Dubai as complete, with a registered completion date of February 2020. Its last site inspection on record was in February 2020. The developer is Emaar Development.

100%

Built, at the site inspection of 10 February 2020

Construction complete

Registered completion date
February 2020
Construction started
January 2013
First registered
January 2014
Units
449
Escrow bank
Mashreq Bank
Name in Arabic
بوليفارد بوينت
Project number
1405
Site inspections
11

Schedule

The register lists Boulevard Point as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2014201620182020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 February 2020

100%+9.9 pts

  • Boulevard Point construction site, inspection photo 1, 10 February 2020
  • Boulevard Point construction site, inspection photo 2, 10 February 2020
  • Boulevard Point construction site, inspection photo 3, 10 February 2020
  • Boulevard Point construction site, inspection photo 4, 10 February 2020

5 August 2019

90%+10.0 pts

  • Boulevard Point construction site, inspection photo 1, 5 August 2019
  • Boulevard Point construction site, inspection photo 2, 5 August 2019
  • Boulevard Point construction site, inspection photo 3, 5 August 2019
  • Boulevard Point construction site, inspection photo 4, 5 August 2019

21 March 2019

80%+10.0 pts

  • Boulevard Point construction site, inspection photo 1, 21 March 2019
  • Boulevard Point construction site, inspection photo 2, 21 March 2019
  • Boulevard Point construction site, inspection photo 3, 21 March 2019
  • Boulevard Point construction site, inspection photo 4, 21 March 2019

28 November 2018

70%+9.1 pts

  • Boulevard Point construction site, inspection photo 1, 28 November 2018
  • Boulevard Point construction site, inspection photo 2, 28 November 2018
  • Boulevard Point construction site, inspection photo 3, 28 November 2018
  • Boulevard Point construction site, inspection photo 4, 28 November 2018

16 August 2018

61%+10 pts

  • Boulevard Point construction site, inspection photo 1, 16 August 2018
  • Boulevard Point construction site, inspection photo 2, 16 August 2018
  • Boulevard Point construction site, inspection photo 3, 16 August 2018
  • Boulevard Point construction site, inspection photo 4, 16 August 2018

3 April 2018

51%+10 pts

  • Boulevard Point construction site, inspection photo 1, 3 April 2018
  • Boulevard Point construction site, inspection photo 2, 3 April 2018
  • Boulevard Point construction site, inspection photo 3, 3 April 2018
  • Boulevard Point construction site, inspection photo 4, 3 April 2018

12 December 2017

41%+10 pts

  • Boulevard Point construction site, inspection photo 1, 12 December 2017
  • Boulevard Point construction site, inspection photo 2, 12 December 2017
  • Boulevard Point construction site, inspection photo 3, 12 December 2017
  • Boulevard Point construction site, inspection photo 4, 12 December 2017

8 August 2017

31%+6.8 pts

  • Boulevard Point construction site, inspection photo 1, 8 August 2017
  • Boulevard Point construction site, inspection photo 2, 8 August 2017
  • Boulevard Point construction site, inspection photo 3, 8 August 2017
  • Boulevard Point construction site, inspection photo 4, 8 August 2017

29 March 2017

24%+9.2 pts

  • Boulevard Point construction site, inspection photo 1, 29 March 2017
  • Boulevard Point construction site, inspection photo 2, 29 March 2017
  • Boulevard Point construction site, inspection photo 3, 29 March 2017
  • Boulevard Point construction site, inspection photo 4, 29 March 2017

12 July 2016

15%+8.8 pts

  • Boulevard Point construction site, inspection photo 1, 12 July 2016
  • Boulevard Point construction site, inspection photo 2, 12 July 2016
  • Boulevard Point construction site, inspection photo 3, 12 July 2016
  • Boulevard Point construction site, inspection photo 4, 12 July 2016

All 114 site photos, by inspection date

Context

DownTown Dubai has 13 projects under construction, 35% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Boulevard Point?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Boulevard Point handover date?
Construction of Boulevard Point is recorded as complete, with a registered completion date of February 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Boulevard Point?
Boulevard Point was 100% built at the site inspection on 10 February 2020. The site has been inspected 11 times since October 2014. The Land Department took 114 site photos at its inspections.
Is Boulevard Point delayed?
The register lists construction as complete.
Who is building Boulevard Point?
The registered developer is Emaar Development. It has 52 other projects under construction in Dubai.
Which bank holds the escrow account for Boulevard Point?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.