Boulevard Point construction photos
114 photos from 11 site inspections, newest first. The percentage is how much of Boulevard Point was built on the day of each visit.
10 February 2020100% built
5 August 201990% built
21 March 201980% built
28 November 201870% built
16 August 201861% built
3 April 201851% built
12 December 201741% built
8 August 201731% built
29 March 201724% built
12 July 201615% built
29 October 20145.7% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.