Blvd Crescent construction progress

The register lists Blvd Crescent in DownTown Dubai as complete, with a registered completion date of May 2019. Its last site inspection on record was in May 2019. The developer is Emaar Development.

100%

Built, at the site inspection of 23 May 2019

Construction complete

Registered completion date
May 2019
Construction started
March 2015
First registered
March 2014
Units
365
Escrow bank
Commercial Bank of Dubai
Name in Arabic
بلوفارد كريسنت
Project number
1494
Site inspections
12

Schedule

The register lists Blvd Crescent as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2016201720182019
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

23 May 2019

100%+8.7 pts

  • Blvd Crescent construction site, inspection photo 1, 23 May 2019
  • Blvd Crescent construction site, inspection photo 2, 23 May 2019
  • Blvd Crescent construction site, inspection photo 3, 23 May 2019
  • Blvd Crescent construction site, inspection photo 4, 23 May 2019

22 January 2019

91%+4.6 pts

  • Blvd Crescent construction site, inspection photo 1, 22 January 2019
  • Blvd Crescent construction site, inspection photo 2, 22 January 2019
  • Blvd Crescent construction site, inspection photo 3, 22 January 2019
  • Blvd Crescent construction site, inspection photo 4, 22 January 2019

8 October 2018

87%+6.4 pts

  • Blvd Crescent construction site, inspection photo 1, 8 October 2018
  • Blvd Crescent construction site, inspection photo 2, 8 October 2018
  • Blvd Crescent construction site, inspection photo 3, 8 October 2018
  • Blvd Crescent construction site, inspection photo 4, 8 October 2018

2 July 2018

80%+5.4 pts

  • Blvd Crescent construction site, inspection photo 1, 2 July 2018
  • Blvd Crescent construction site, inspection photo 2, 2 July 2018
  • Blvd Crescent construction site, inspection photo 3, 2 July 2018
  • Blvd Crescent construction site, inspection photo 4, 2 July 2018

27 May 2018

75%+8.5 pts

  • Blvd Crescent construction site, inspection photo 1, 27 May 2018
  • Blvd Crescent construction site, inspection photo 2, 27 May 2018
  • Blvd Crescent construction site, inspection photo 3, 27 May 2018
  • Blvd Crescent construction site, inspection photo 4, 27 May 2018

21 March 2018

66%+13 pts

  • Blvd Crescent construction site, inspection photo 1, 21 March 2018
  • Blvd Crescent construction site, inspection photo 2, 21 March 2018
  • Blvd Crescent construction site, inspection photo 3, 21 March 2018
  • Blvd Crescent construction site, inspection photo 4, 21 March 2018

8 January 2018

54%+22 pts

  • Blvd Crescent construction site, inspection photo 1, 8 January 2018
  • Blvd Crescent construction site, inspection photo 2, 8 January 2018
  • Blvd Crescent construction site, inspection photo 3, 8 January 2018
  • Blvd Crescent construction site, inspection photo 4, 8 January 2018

24 July 2017

32%+11 pts

  • Blvd Crescent construction site, inspection photo 1, 24 July 2017
  • Blvd Crescent construction site, inspection photo 2, 24 July 2017
  • Blvd Crescent construction site, inspection photo 3, 24 July 2017
  • Blvd Crescent construction site, inspection photo 4, 24 July 2017

29 March 2017

21%+4.9 pts

  • Blvd Crescent construction site, inspection photo 1, 29 March 2017
  • Blvd Crescent construction site, inspection photo 2, 29 March 2017
  • Blvd Crescent construction site, inspection photo 3, 29 March 2017
  • Blvd Crescent construction site, inspection photo 4, 29 March 2017

21 December 2016

16%+6.9 pts

  • Blvd Crescent construction site, inspection photo 1, 21 December 2016
  • Blvd Crescent construction site, inspection photo 2, 21 December 2016
  • Blvd Crescent construction site, inspection photo 3, 21 December 2016
  • Blvd Crescent construction site, inspection photo 4, 21 December 2016

All 107 site photos, by inspection date

Context

DownTown Dubai has 13 projects under construction, 35% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Blvd Crescent?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Blvd Crescent handover date?
Construction of Blvd Crescent is recorded as complete, with a registered completion date of May 2019. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Blvd Crescent?
Blvd Crescent was 100% built at the site inspection on 23 May 2019. The site has been inspected 12 times since March 2015. The Land Department took 107 site photos at its inspections.
Is Blvd Crescent delayed?
The register lists construction as complete.
Who is building Blvd Crescent?
The registered developer is Emaar Development. It has 52 other projects under construction in Dubai.
Which bank holds the escrow account for Blvd Crescent?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.