Blvd Crescent construction photos

107 photos from 12 site inspections, newest first. The percentage is how much of Blvd Crescent was built on the day of each visit.

23 May 2019100% built

22 January 201991% built

8 October 201887% built

2 July 201880% built

27 May 201875% built

21 March 201866% built

8 January 201854% built

24 July 201732% built

29 March 201721% built

21 December 201616% built

17 July 20169.2% built

8 March 20153.8% built

Back to Blvd Crescent construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.