Sky Gate Tower construction progress

Sky Gate Tower in Jumeirah Village Triangle is 1.6% built at the Land Department inspection of March 2026. Developer Tiger Properties. Completion registered for February 2028.

4.7%

Built, at the Land Department site inspection of 31 March 2026

Running behind its date

Completion date (Land Department)
February 2028
Finish at recent pace
September 2057
Construction started
September 2025
Registered with the Land Department
October 2025
Units
431
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
سكاى جيت تاور
Land Department project number
4120
Land Department site inspections
2

Schedule

Between September 2025 and March 2026 the site added about 0.3 points a month. At that rate it would finish around September 2057, more than three months after the February 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

31 March 2026

1.6%+1.6 pts

  • Sky Gate Tower construction site, Land Department inspection photo 1, 31 March 2026
  • Sky Gate Tower construction site, Land Department inspection photo 2, 31 March 2026
  • Sky Gate Tower construction site, Land Department inspection photo 3, 31 March 2026
  • Sky Gate Tower construction site, Land Department inspection photo 4, 31 March 2026

30 September 2025

0%

  • Sky Gate Tower construction site, Land Department inspection photo 1, 30 September 2025
  • Sky Gate Tower construction site, Land Department inspection photo 2, 30 September 2025

All 6 site photos, by inspection date

Context

Jumeirah Village Triangle has 31 projects under construction, 28% built on average.

Tiger Properties has 9 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Sky Gate Tower?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Sky Gate Tower be completed?
The completion date registered with the Dubai Land Department is February 2028. At the pace of its recent inspections the site would reach 100% around September 2057. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Sky Gate Tower is built?
4.7%, measured at the Land Department site inspection on 31 March 2026. The Land Department engineers have inspected the site 2 times since September 2025.
Is Sky Gate Tower delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2028.
Who is building Sky Gate Tower?
The registered developer is Tiger Properties. It has 8 other projects under construction in Dubai.
Which bank holds the escrow account for Sky Gate Tower?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.