Zada Tower construction progress

The register lists Zada Tower in Business Bay as complete, with a registered completion date of June 2023. Its last site inspection on record was in January 2023. The developer is Island Oasis Properties.

100%

Built, at the site inspection of 23 January 2023

Construction complete

Registered completion date
June 2023
Construction started
April 2019
First registered
April 2019
Community
Business Bay
Units
703
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
زادا تاور
Project number
2155
Site inspections
10

Schedule

The register lists Zada Tower as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2020202120222023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

23 January 2023

100%+4.8 pts

  • Zada Tower construction site, inspection photo 1, 23 January 2023
  • Zada Tower construction site, inspection photo 2, 23 January 2023
  • Zada Tower construction site, inspection photo 3, 23 January 2023
  • Zada Tower construction site, inspection photo 4, 23 January 2023

27 September 2022

95%+18 pts

  • Zada Tower construction site, inspection photo 1, 27 September 2022
  • Zada Tower construction site, inspection photo 2, 27 September 2022
  • Zada Tower construction site, inspection photo 3, 27 September 2022
  • Zada Tower construction site, inspection photo 4, 27 September 2022

8 June 2022

77%+19 pts

  • Zada Tower construction site, inspection photo 1, 8 June 2022
  • Zada Tower construction site, inspection photo 2, 8 June 2022
  • Zada Tower construction site, inspection photo 3, 8 June 2022
  • Zada Tower construction site, inspection photo 4, 8 June 2022

24 January 2022

58%+28 pts

  • Zada Tower construction site, inspection photo 1, 24 January 2022
  • Zada Tower construction site, inspection photo 2, 24 January 2022
  • Zada Tower construction site, inspection photo 3, 24 January 2022
  • Zada Tower construction site, inspection photo 4, 24 January 2022

15 August 2021

30%+10 pts

  • Zada Tower construction site, inspection photo 1, 15 August 2021
  • Zada Tower construction site, inspection photo 2, 15 August 2021
  • Zada Tower construction site, inspection photo 3, 15 August 2021
  • Zada Tower construction site, inspection photo 4, 15 August 2021

22 March 2021

20%+10 pts

  • Zada Tower construction site, inspection photo 1, 22 March 2021
  • Zada Tower construction site, inspection photo 2, 22 March 2021
  • Zada Tower construction site, inspection photo 3, 22 March 2021
  • Zada Tower construction site, inspection photo 4, 22 March 2021

24 November 2020

9.9%+2.2 pts

  • Zada Tower construction site, inspection photo 1, 24 November 2020
  • Zada Tower construction site, inspection photo 2, 24 November 2020
  • Zada Tower construction site, inspection photo 3, 24 November 2020
  • Zada Tower construction site, inspection photo 4, 24 November 2020

9 July 2020

7.7%

  • Zada Tower construction site, inspection photo 1, 9 July 2020
  • Zada Tower construction site, inspection photo 2, 9 July 2020

2 March 2020

7.7%+2.0 pts

  • Zada Tower construction site, inspection photo 1, 2 March 2020
  • Zada Tower construction site, inspection photo 2, 2 March 2020
  • Zada Tower construction site, inspection photo 3, 2 March 2020
  • Zada Tower construction site, inspection photo 4, 2 March 2020

28 October 2019

5.7%

  • Zada Tower construction site, inspection photo 1, 28 October 2019
  • Zada Tower construction site, inspection photo 2, 28 October 2019
  • Zada Tower construction site, inspection photo 3, 28 October 2019
  • Zada Tower construction site, inspection photo 4, 28 October 2019

All 84 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Island Oasis Properties has 26 projects under construction in Dubai; 7 have passed their registered completion date.

Own a unit in Zada Tower?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Zada Tower handover date?
Construction of Zada Tower is recorded as complete, with a registered completion date of June 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Zada Tower?
Zada Tower was 100% built at the site inspection on 23 January 2023. The site has been inspected 10 times since October 2019. The Land Department took 84 site photos at its inspections.
Is Zada Tower delayed?
The register lists construction as complete.
Who is building Zada Tower?
The registered developer is Island Oasis Properties. It has 26 other projects under construction in Dubai.
Which bank holds the escrow account for Zada Tower?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.