Damac Lagoons - Nice 1 construction progress
Damac Lagoons - Nice 1 in Damac Lagoons is 94% built at the Land Department inspection of August 2026. Developer Island Oasis Properties. Completion registered for July 2025.
94%
Built, at the Land Department site inspection of 10 August 2026
15 months past its registered completion date
- Completion date (Land Department)
- July 2025
- Finish at recent pace
- November 2026
- Construction started
- February 2022
- Registered with the Land Department
- December 2021
- Developer
- Island Oasis Properties
- Community
- Damac Lagoons
- Units
- 509
- Escrow bank
- Emirates NBD
- Name in Arabic
- داماك لاجونز - نيس 1
- Land Department project number
- 2335
- Land Department site inspections
- 11
Schedule
Damac Lagoons - Nice 1 was registered to complete in July 2025, 15 months ago, and is still under construction. Over the last year of inspections it has added about 1.8 points a month. Kept at that rate, the site would reach 100% around November 2026.
Site inspections
10 August 2026
94%+0.9 pts
9 June 2026
93%+14 pts
20 November 2025
78%+10 pts
23 June 2025
68%+10 pts
24 February 2025
58%+6.6 pts
22 September 2024
51%+17 pts
1 May 2024
34%+18 pts
9 October 2023
16%+8.7 pts
12 June 2023
7.4%+6.8 pts
3 February 2023
0.5%+0.4 pts
Context
Damac Lagoons has 6 projects under construction, 82% built on average.
Island Oasis Properties has 27 projects under construction in Dubai; 6 have passed their registered completion date.
Own a unit in Damac Lagoons - Nice 1?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Damac Lagoons - Nice 1 be completed?
- The completion date registered with the Dubai Land Department is July 2025. At the pace of its recent inspections the site would reach 100% around November 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Damac Lagoons - Nice 1 is built?
- 94%, measured at the Land Department site inspection on 10 August 2026. The Land Department engineers have inspected the site 11 times since August 2022.
- Is Damac Lagoons - Nice 1 delayed?
- Yes. Its registered completion date of July 2025 has passed and the Land Department still lists it as under construction.
- Who is building Damac Lagoons - Nice 1?
- The registered developer is Island Oasis Properties. It has 26 other projects under construction in Dubai.
- Which bank holds the escrow account for Damac Lagoons - Nice 1?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Damac Lagoons - Nice 2Also by Island Oasis Properties. 84%.
- Damac Lagoons - PortofinoAlso by Island Oasis Properties. 97%, Due June 2025, passed.
- Damac Lagoons - Venice (1)Also by Island Oasis Properties. 74%, Due September 2025, passed.
- Damac Lagoons - IbizaAlso by Island Oasis Properties. 79%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)