Damac Lagoons - Venice (1) construction progress

Damac Lagoons - Venice (1) in Damac Lagoons is 74% built at the Land Department inspection of July 2026. Developer Island Oasis Properties. Completion registered for September 2025.

74%

Built, at the Land Department site inspection of 17 July 2026

12 months past its registered completion date

Completion date (Land Department)
September 2025
Finish at recent pace
December 2027
Construction started
December 2022
Registered with the Land Department
May 2022
Community
Damac Lagoons
Units
424
Escrow bank
Emirates NBD
Name in Arabic
داماك لاجونز - فينيس (1)
Land Department project number
2396
Land Department site inspections
11

Schedule

Damac Lagoons - Venice (1) was registered to complete in September 2025, 12 months ago, and is still under construction. Over the last year of inspections it has added about 1.5 points a month. Kept at that rate, the site would reach 100% around December 2027.

0%25%50%75%100%2023202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

17 July 2026

74%+6.4 pts

  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 1, 17 July 2026
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 2, 17 July 2026
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 3, 17 July 2026
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 4, 17 July 2026

22 April 2026

68%+6.0 pts

  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 1, 22 April 2026
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 2, 22 April 2026
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 3, 22 April 2026
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 4, 22 April 2026

13 November 2025

62%+7.2 pts

  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 1, 13 November 2025
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 2, 13 November 2025
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 3, 13 November 2025
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 4, 13 November 2025

24 June 2025

55%+4.8 pts

  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 1, 24 June 2025
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 2, 24 June 2025
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 3, 24 June 2025
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 4, 24 June 2025

6 February 2025

50%+13 pts

  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 1, 6 February 2025
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 2, 6 February 2025
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 3, 6 February 2025
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 4, 6 February 2025

19 September 2024

37%+14 pts

  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 1, 19 September 2024
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 2, 19 September 2024
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 3, 19 September 2024
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 4, 19 September 2024

20 May 2024

23%+17 pts

  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 1, 20 May 2024
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 2, 20 May 2024
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 3, 20 May 2024
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 4, 20 May 2024

7 December 2023

6.2%+4.5 pts

  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 1, 7 December 2023
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 2, 7 December 2023
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 3, 7 December 2023
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 4, 7 December 2023

22 August 2023

1.6%+1.2 pts

  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 1, 22 August 2023
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 2, 22 August 2023
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 3, 22 August 2023
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 4, 22 August 2023

4 May 2023

0.4%+0.3 pts

  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 1, 4 May 2023
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 2, 4 May 2023
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 3, 4 May 2023
  • Damac Lagoons - Venice (1) construction site, Land Department inspection photo 4, 4 May 2023

All 62 site photos, by inspection date

Context

Damac Lagoons has 6 projects under construction, 82% built on average.

Island Oasis Properties has 27 projects under construction in Dubai; 6 have passed their registered completion date.

Own a unit in Damac Lagoons - Venice (1)?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Damac Lagoons - Venice (1) be completed?
The completion date registered with the Dubai Land Department is September 2025. At the pace of its recent inspections the site would reach 100% around December 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Damac Lagoons - Venice (1) is built?
74%, measured at the Land Department site inspection on 17 July 2026. The Land Department engineers have inspected the site 11 times since December 2022.
Is Damac Lagoons - Venice (1) delayed?
Yes. Its registered completion date of September 2025 has passed and the Land Department still lists it as under construction.
Who is building Damac Lagoons - Venice (1)?
The registered developer is Island Oasis Properties. It has 26 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Lagoons - Venice (1)?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.