Damac Lagoons - Venice (1) construction progress

Damac Lagoons - Venice (1) in Damac Lagoons was registered to complete in September 2025 and is still under construction. At the last site inspection, in July 2026, it was 74% built. The developer is Island Oasis Properties.

74%

Built, at the site inspection of 17 July 2026

14 months past its registered completion date

Registered completion date
September 2025
Finish at recent pace
December 2027
Construction started
December 2022
First registered
May 2022
Community
Damac Lagoons
Units
424
Escrow bank
Emirates NBD
Name in Arabic
داماك لاجونز - فينيس (1)
Project number
2396
Site inspections
11

Schedule

Damac Lagoons - Venice (1) was registered to complete in September 2025, 14 months ago, and is still under construction. Over the last year of inspections it has added about 1.5 points a month. Kept at that rate, the site would reach 100% around December 2027.

0%25%50%75%100%2023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 July 2026

74%+6.4 pts

  • Damac Lagoons - Venice (1) construction site, inspection photo 1, 17 July 2026
  • Damac Lagoons - Venice (1) construction site, inspection photo 2, 17 July 2026
  • Damac Lagoons - Venice (1) construction site, inspection photo 3, 17 July 2026
  • Damac Lagoons - Venice (1) construction site, inspection photo 4, 17 July 2026

22 April 2026

68%+6.0 pts

  • Damac Lagoons - Venice (1) construction site, inspection photo 1, 22 April 2026
  • Damac Lagoons - Venice (1) construction site, inspection photo 2, 22 April 2026
  • Damac Lagoons - Venice (1) construction site, inspection photo 3, 22 April 2026
  • Damac Lagoons - Venice (1) construction site, inspection photo 4, 22 April 2026

13 November 2025

62%+7.2 pts

  • Damac Lagoons - Venice (1) construction site, inspection photo 1, 13 November 2025
  • Damac Lagoons - Venice (1) construction site, inspection photo 2, 13 November 2025
  • Damac Lagoons - Venice (1) construction site, inspection photo 3, 13 November 2025
  • Damac Lagoons - Venice (1) construction site, inspection photo 4, 13 November 2025

24 June 2025

55%+4.8 pts

  • Damac Lagoons - Venice (1) construction site, inspection photo 1, 24 June 2025
  • Damac Lagoons - Venice (1) construction site, inspection photo 2, 24 June 2025
  • Damac Lagoons - Venice (1) construction site, inspection photo 3, 24 June 2025
  • Damac Lagoons - Venice (1) construction site, inspection photo 4, 24 June 2025

6 February 2025

50%+13 pts

  • Damac Lagoons - Venice (1) construction site, inspection photo 1, 6 February 2025
  • Damac Lagoons - Venice (1) construction site, inspection photo 2, 6 February 2025
  • Damac Lagoons - Venice (1) construction site, inspection photo 3, 6 February 2025
  • Damac Lagoons - Venice (1) construction site, inspection photo 4, 6 February 2025

19 September 2024

37%+14 pts

  • Damac Lagoons - Venice (1) construction site, inspection photo 1, 19 September 2024
  • Damac Lagoons - Venice (1) construction site, inspection photo 2, 19 September 2024
  • Damac Lagoons - Venice (1) construction site, inspection photo 3, 19 September 2024
  • Damac Lagoons - Venice (1) construction site, inspection photo 4, 19 September 2024

20 May 2024

23%+17 pts

  • Damac Lagoons - Venice (1) construction site, inspection photo 1, 20 May 2024
  • Damac Lagoons - Venice (1) construction site, inspection photo 2, 20 May 2024
  • Damac Lagoons - Venice (1) construction site, inspection photo 3, 20 May 2024
  • Damac Lagoons - Venice (1) construction site, inspection photo 4, 20 May 2024

7 December 2023

6.2%+4.5 pts

  • Damac Lagoons - Venice (1) construction site, inspection photo 1, 7 December 2023
  • Damac Lagoons - Venice (1) construction site, inspection photo 2, 7 December 2023
  • Damac Lagoons - Venice (1) construction site, inspection photo 3, 7 December 2023
  • Damac Lagoons - Venice (1) construction site, inspection photo 4, 7 December 2023

22 August 2023

1.6%+1.2 pts

  • Damac Lagoons - Venice (1) construction site, inspection photo 1, 22 August 2023
  • Damac Lagoons - Venice (1) construction site, inspection photo 2, 22 August 2023
  • Damac Lagoons - Venice (1) construction site, inspection photo 3, 22 August 2023
  • Damac Lagoons - Venice (1) construction site, inspection photo 4, 22 August 2023

4 May 2023

0.4%+0.3 pts

  • Damac Lagoons - Venice (1) construction site, inspection photo 1, 4 May 2023
  • Damac Lagoons - Venice (1) construction site, inspection photo 2, 4 May 2023
  • Damac Lagoons - Venice (1) construction site, inspection photo 3, 4 May 2023
  • Damac Lagoons - Venice (1) construction site, inspection photo 4, 4 May 2023

All 62 site photos, by inspection date

Context

Damac Lagoons has 5 projects under construction, 79% built on average.

Island Oasis Properties has 26 projects under construction in Dubai; 7 have passed their registered completion date.

Own a unit in Damac Lagoons - Venice (1)?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Damac Lagoons - Venice (1) handover date?
The registered completion date was September 2025, and the register still lists Damac Lagoons - Venice (1) as under construction. At the pace of its recent inspections the site would reach 100% around December 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Damac Lagoons - Venice (1)?
Damac Lagoons - Venice (1) was 74% built at the site inspection on 17 July 2026. The site has been inspected 11 times since December 2022. The Land Department took 62 site photos at its inspections.
Is Damac Lagoons - Venice (1) delayed?
Yes. Its registered completion date of September 2025 has passed and the project is still listed as under construction.
Who is building Damac Lagoons - Venice (1)?
The registered developer is Island Oasis Properties. It has 25 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Lagoons - Venice (1)?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.