Sol Avenue construction progress

The register lists Sol Avenue in Business Bay as complete, with a registered completion date of May 2020. Its last site inspection on record was in March 2021. The developer is S O L Properties Development.

100%

Built, at the site inspection of 28 March 2021

Construction complete

Registered completion date
May 2020
Construction started
February 2015
First registered
May 2015
Community
Business Bay
Units
324
Escrow bank
Dubai Islamic Bank
Name in Arabic
شارع سول
Project number
629
Site inspections
13

Schedule

The register lists Sol Avenue as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201620182020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 March 2021

100%+1.3 pts

  • Sol Avenue construction site, inspection photo 1, 28 March 2021
  • Sol Avenue construction site, inspection photo 2, 28 March 2021
  • Sol Avenue construction site, inspection photo 3, 28 March 2021
  • Sol Avenue construction site, inspection photo 4, 28 March 2021

13 January 2021

99%+14 pts

  • Sol Avenue construction site, inspection photo 1, 13 January 2021
  • Sol Avenue construction site, inspection photo 2, 13 January 2021
  • Sol Avenue construction site, inspection photo 3, 13 January 2021
  • Sol Avenue construction site, inspection photo 4, 13 January 2021

11 June 2020

85%+10 pts

  • Sol Avenue construction site, inspection photo 1, 11 June 2020
  • Sol Avenue construction site, inspection photo 2, 11 June 2020
  • Sol Avenue construction site, inspection photo 3, 11 June 2020
  • Sol Avenue construction site, inspection photo 4, 11 June 2020

21 January 2020

75%+15 pts

  • Sol Avenue construction site, inspection photo 1, 21 January 2020
  • Sol Avenue construction site, inspection photo 2, 21 January 2020
  • Sol Avenue construction site, inspection photo 3, 21 January 2020
  • Sol Avenue construction site, inspection photo 4, 21 January 2020

4 September 2019

60%+7.4 pts

  • Sol Avenue construction site, inspection photo 1, 4 September 2019
  • Sol Avenue construction site, inspection photo 2, 4 September 2019
  • Sol Avenue construction site, inspection photo 3, 4 September 2019
  • Sol Avenue construction site, inspection photo 4, 4 September 2019

19 May 2019

53%+9.4 pts

  • Sol Avenue construction site, inspection photo 1, 19 May 2019
  • Sol Avenue construction site, inspection photo 2, 19 May 2019
  • Sol Avenue construction site, inspection photo 3, 19 May 2019
  • Sol Avenue construction site, inspection photo 4, 19 May 2019

6 March 2019

43%+21 pts

  • Sol Avenue construction site, inspection photo 1, 6 March 2019
  • Sol Avenue construction site, inspection photo 2, 6 March 2019
  • Sol Avenue construction site, inspection photo 3, 6 March 2019
  • Sol Avenue construction site, inspection photo 4, 6 March 2019

18 September 2018

22%+10 pts

  • Sol Avenue construction site, inspection photo 1, 18 September 2018
  • Sol Avenue construction site, inspection photo 2, 18 September 2018
  • Sol Avenue construction site, inspection photo 3, 18 September 2018
  • Sol Avenue construction site, inspection photo 4, 18 September 2018

17 April 2018

12%+4.3 pts

  • Sol Avenue construction site, inspection photo 1, 17 April 2018
  • Sol Avenue construction site, inspection photo 2, 17 April 2018
  • Sol Avenue construction site, inspection photo 3, 17 April 2018
  • Sol Avenue construction site, inspection photo 4, 17 April 2018

4 January 2018

7.7%+1.0 pts

  • Sol Avenue construction site, inspection photo 1, 4 January 2018
  • Sol Avenue construction site, inspection photo 2, 4 January 2018
  • Sol Avenue construction site, inspection photo 3, 4 January 2018
  • Sol Avenue construction site, inspection photo 4, 4 January 2018

All 111 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

S O L Properties Development has 6 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Sol Avenue?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Sol Avenue handover date?
Construction of Sol Avenue is recorded as complete, with a registered completion date of May 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Sol Avenue?
Sol Avenue was 100% built at the site inspection on 28 March 2021. The site has been inspected 13 times since June 2015. The Land Department took 111 site photos at its inspections.
Is Sol Avenue delayed?
The register lists construction as complete.
Who is building Sol Avenue?
The registered developer is S O L Properties Development. It has 6 other projects under construction in Dubai.
Which bank holds the escrow account for Sol Avenue?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.