Sol Levante construction progress

The registered completion date for Sol Levante in Jumeirah Village Triangle is September 2028. At the last site inspection, in July 2026, it was 7.2% built. The developer is S O L Properties Development.

7.2%

Built, at the site inspection of 6 July 2026

Running behind its date

Registered completion date
September 2028
Finish at recent pace
August 2037
Construction started
June 2025
First registered
May 2025
Units
674
Escrow bank
Emirates NBD
Name in Arabic
سول ليفانتي
Project number
3642
Site inspections
3

Schedule

Between September 2025 and July 2026 the site added about 0.7 points a month. At that rate it would finish around August 2037, more than three months after its registered date of September 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

6 July 2026

7.2%+7.0 pts

  • Sol Levante construction site, inspection photo 1, 6 July 2026
  • Sol Levante construction site, inspection photo 2, 6 July 2026
  • Sol Levante construction site, inspection photo 3, 6 July 2026
  • Sol Levante construction site, inspection photo 4, 6 July 2026

3 September 2025

0.2%+0.2 pts

  • Sol Levante construction site, inspection photo 1, 3 September 2025
  • Sol Levante construction site, inspection photo 2, 3 September 2025
  • Sol Levante construction site, inspection photo 3, 3 September 2025

2 April 2025

0%

  • Sol Levante construction site, inspection photo 1, 2 April 2025
  • Sol Levante construction site, inspection photo 2, 2 April 2025

All 11 site photos, by inspection date

Context

Jumeirah Village Triangle has 29 projects under construction, 27% built on average.

S O L Properties Development has 6 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Sol Levante?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Sol Levante handover date?
The registered completion date is September 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2037. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Sol Levante?
Sol Levante was 7.2% built at the site inspection on 6 July 2026. The site has been inspected 3 times since April 2025. The Land Department took 11 site photos at its inspections.
Is Sol Levante delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
Who is building Sol Levante?
The registered developer is S O L Properties Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Sol Levante?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.