Sol Levante construction progress
The registered completion date for Sol Levante in Jumeirah Village Triangle is September 2028. At the last site inspection, in July 2026, it was 7.2% built. The developer is S O L Properties Development.
7.2%
Built, at the site inspection of 6 July 2026
Running behind its date
- Registered completion date
- September 2028
- Finish at recent pace
- August 2037
- Construction started
- June 2025
- First registered
- May 2025
- Developer
- S O L Properties Development
- Community
- Jumeirah Village Triangle
- Units
- 674
- Escrow bank
- Emirates NBD
- Name in Arabic
- سول ليفانتي
- Project number
- 3642
- Site inspections
- 3
Schedule
Between September 2025 and July 2026 the site added about 0.7 points a month. At that rate it would finish around August 2037, more than three months after its registered date of September 2028.
Site inspections
6 July 2026
7.2%+7.0 pts
3 September 2025
0.2%+0.2 pts
2 April 2025
0%
Context
Jumeirah Village Triangle has 29 projects under construction, 27% built on average.
S O L Properties Development has 6 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Sol Levante?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Sol Levante handover date?
- The registered completion date is September 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2037. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Sol Levante?
- Sol Levante was 7.2% built at the site inspection on 6 July 2026. The site has been inspected 3 times since April 2025. The Land Department took 11 site photos at its inspections.
- Is Sol Levante delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
- Who is building Sol Levante?
- The registered developer is S O L Properties Development. It has 5 other projects under construction in Dubai.
- Which bank holds the escrow account for Sol Levante?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Solara Tower DubaiAlso by S O L Properties Development. 21%, Due August 2027.
- Sol LuxeAlso by S O L Properties Development. 2.0%, Due March 2029.
- Sol Terra Casa IIAlso by S O L Properties Development. 0%, Due June 2028.
- Sol Terra GardensAlso by S O L Properties Development. 0%, Due May 2029.
- Paradise OneNearby in Jumeirah Village Triangle. 70%, Due April 2027.
- Silver StallionsNearby in Jumeirah Village Triangle. 12%, Due December 2017, passed.
- Fashionz 1 By DanubeNearby in Jumeirah Village Triangle. 40%.
- Volga TowerNearby in Jumeirah Village Triangle. 51%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.