Solara Tower Dubai construction progress

The registered completion date for Solara Tower Dubai in DownTown Dubai is August 2027. At the last site inspection, in June 2026, it was 21% built. The developer is S O L Properties Development.

21%

Built, at the site inspection of 30 June 2026

Running behind its date

Registered completion date
August 2027
Finish at recent pace
April 2033
Construction started
August 2024
First registered
August 2024
Units
231
Escrow bank
Emirates NBD
Name in Arabic
سولارا تاور دبي
Project number
2928
Site inspections
4

Schedule

Between August 2025 and June 2026 the site added about 1.0 points a month. At that rate it would finish around April 2033, more than three months after its registered date of August 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 June 2026

21%+9.8 pts

  • Solara Tower Dubai construction site, inspection photo 1, 30 June 2026
  • Solara Tower Dubai construction site, inspection photo 2, 30 June 2026
  • Solara Tower Dubai construction site, inspection photo 3, 30 June 2026
  • Solara Tower Dubai construction site, inspection photo 4, 30 June 2026

27 August 2025

11%+3.3 pts

  • Solara Tower Dubai construction site, inspection photo 1, 27 August 2025
  • Solara Tower Dubai construction site, inspection photo 2, 27 August 2025
  • Solara Tower Dubai construction site, inspection photo 3, 27 August 2025
  • Solara Tower Dubai construction site, inspection photo 4, 27 August 2025

18 March 2025

7.7%+7.7 pts

  • Solara Tower Dubai construction site, inspection photo 1, 18 March 2025
  • Solara Tower Dubai construction site, inspection photo 2, 18 March 2025
  • Solara Tower Dubai construction site, inspection photo 3, 18 March 2025
  • Solara Tower Dubai construction site, inspection photo 4, 18 March 2025

31 July 2024

0%

  • Solara Tower Dubai construction site, inspection photo 1, 31 July 2024
  • Solara Tower Dubai construction site, inspection photo 2, 31 July 2024

All 17 site photos, by inspection date

Context

DownTown Dubai has 13 projects under construction, 35% built on average.

S O L Properties Development has 6 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Solara Tower Dubai?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Solara Tower Dubai handover date?
The registered completion date is August 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Solara Tower Dubai?
Solara Tower Dubai was 21% built at the site inspection on 30 June 2026. The site has been inspected 4 times since July 2024. The Land Department took 17 site photos at its inspections.
Is Solara Tower Dubai delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
Who is building Solara Tower Dubai?
The registered developer is S O L Properties Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Solara Tower Dubai?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.