Royal Regency Suites construction photos

88 photos from 12 site inspections, newest first. The percentage is how much of Royal Regency Suites was built on the day of each visit.

27 October 202657% built

19 August 202656% built

22 June 202654% built

23 March 202647% built

22 December 202542% built

29 August 202533% built

28 July 202528% built

17 June 202526% built

6 March 202520% built

18 December 202411% built

5 November 20249.5% built

26 September 20232.0% built

Back to Royal Regency Suites construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.