41 photos taken by Dubai Land Department engineers at 7 site inspections, newest first. The percentage is how much of Onda By Kasco was built on the day of each visit.

19 August 202661% built

7 May 202651% built

29 January 202636% built

15 September 202521% built

28 May 202514% built

12 February 20258.6% built

10 May 20240% built

Back to Onda By Kasco construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.