Onda By Kasco construction photos
41 photos taken by Dubai Land Department engineers at 7 site inspections, newest first. The percentage is how much of Onda By Kasco was built on the day of each visit.
19 August 202661% built
7 May 202651% built
29 January 202636% built
15 September 202521% built
28 May 202514% built
12 February 20258.6% built
10 May 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.