Luxury Family Residence III construction photos
42 photos from 7 site inspections, newest first. The percentage is how much of Luxury Family Residence III was built on the day of each visit.
7 May 202651% built
24 November 202546% built
19 March 202540% built
2 October 202436% built
15 February 202430% built
16 August 202323% built
10 October 20224.1% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.