Sobha Estates construction progress
The registered completion date for Sobha Estates in Bukadra is December 2027. At the last site inspection, in September 2026, it was 68% built. The developer is Sobha.
68%
Built, at the site inspection of 15 September 2026
On pace for its date
Schedule
Since October 2025 Sobha Estates has added about 2.6 points a month. That puts 100% around September 2027, within three months of its registered completion date of December 2027.
Site inspections
15 September 2026
68%+7.3 pts
11 June 2026
61%+9.2 pts
18 March 2026
52%+10 pts
30 October 2025
42%+7.5 pts
18 September 2024
34%+17 pts
23 April 2024
17%+15 pts
13 October 2023
2.2%
Context
Bukadra has 21 projects under construction, 27% built on average.
Sobha has 27 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Sobha Estates?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Sobha Estates handover date?
- The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Sobha Estates?
- Sobha Estates was 68% built at the site inspection on 15 September 2026. The site has been inspected 7 times since October 2023. The Land Department took 38 site photos at its inspections.
- Is Sobha Estates delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2027.
- Who is building Sobha Estates?
- The registered developer is Sobha. It has 26 other projects under construction in Dubai.
- Which bank holds the escrow account for Sobha Estates?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sobha Seahaven Tower AAlso by Sobha. 45%, Due April 2028.
- Verde By SobhaAlso by Sobha. 85%, Due June 2027.
- Sobha Creek Vista HeightsAlso by Sobha. 92%.
- Sobha Seahaven Tower B & CAlso by Sobha. 40%, Due October 2028.
- Claydon House By EllingtonNearby in Bukadra. 16%, Due December 2027.
- The Waterway By Prestige OneNearby in Bukadra. 15%, Due June 2027.
- Parkway By Prestige OneNearby in Bukadra. 11%, Due January 2028.
- Ayaan Heights INearby in Bukadra. 20%, Due March 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.