Skyscape construction progress

Skyscape in Bukadra is 38% built at the Land Department inspection of September 2026. Developer Sobha. Completion registered for December 2029.

38%

Built, at the Land Department site inspection of 21 September 2026

On pace for its date

Completion date (Land Department)
December 2029
Finish at recent pace
September 2028
Construction started
August 2024
Registered with the Land Department
October 2024
Developer
Sobha
Community
Bukadra
Units
1,852
Escrow bank
Dubai Islamic Bank
Name in Arabic
سكاي سكيب
Land Department project number
3160
Land Department site inspections
5

Schedule

Since March 2026 Skyscape has added about 2.6 points a month. That puts 100% around September 2028, within three months of its registered completion date of December 2029.

0%25%50%75%100%20252026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

21 September 2026

38%+8.2 pts

  • Skyscape construction site, Land Department inspection photo 1, 21 September 2026
  • Skyscape construction site, Land Department inspection photo 2, 21 September 2026
  • Skyscape construction site, Land Department inspection photo 3, 21 September 2026
  • Skyscape construction site, Land Department inspection photo 4, 21 September 2026

16 June 2026

30%+6.9 pts

  • Skyscape construction site, Land Department inspection photo 1, 16 June 2026
  • Skyscape construction site, Land Department inspection photo 2, 16 June 2026
  • Skyscape construction site, Land Department inspection photo 3, 16 June 2026
  • Skyscape construction site, Land Department inspection photo 4, 16 June 2026

31 March 2026

23%+11 pts

  • Skyscape construction site, Land Department inspection photo 1, 31 March 2026
  • Skyscape construction site, Land Department inspection photo 2, 31 March 2026
  • Skyscape construction site, Land Department inspection photo 3, 31 March 2026
  • Skyscape construction site, Land Department inspection photo 4, 31 March 2026

4 July 2025

12%+12 pts

  • Skyscape construction site, Land Department inspection photo 1, 4 July 2025
  • Skyscape construction site, Land Department inspection photo 2, 4 July 2025
  • Skyscape construction site, Land Department inspection photo 3, 4 July 2025
  • Skyscape construction site, Land Department inspection photo 4, 4 July 2025

22 July 2024

0%

  • Skyscape construction site, Land Department inspection photo 1, 22 July 2024
  • Skyscape construction site, Land Department inspection photo 2, 22 July 2024
  • Skyscape construction site, Land Department inspection photo 3, 22 July 2024

All 44 site photos, by inspection date

Context

Bukadra has 21 projects under construction, 26% built on average.

Sobha has 27 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Skyscape?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Skyscape be completed?
The completion date registered with the Dubai Land Department is December 2029. At the pace of its recent inspections the site would reach 100% around September 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Skyscape is built?
38%, measured at the Land Department site inspection on 21 September 2026. The Land Department engineers have inspected the site 5 times since July 2024.
Is Skyscape delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2029.
Who is building Skyscape?
The registered developer is Sobha. It has 26 other projects under construction in Dubai.
Which bank holds the escrow account for Skyscape?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.