Skip to content

Skyscape construction progress

The registered completion date for Skyscape in Bukadra is December 2029. At the last site inspection, in September 2026, it was 38% built. The developer is Sobha.

38%

Built, at the site inspection of 21 September 2026

On pace for its date

Registered completion date
December 2029
Finish at recent pace
September 2028
Construction started
August 2024
First registered
October 2024
Developer
Sobha
Community
Bukadra
Units
1,852
Escrow bank
Dubai Islamic Bank
Name in Arabic
سكاي سكيب
Project number
3160
Site inspections
5

Schedule

Since March 2026 Skyscape has added about 2.6 points a month. That puts 100% around September 2028, within three months of its registered completion date of December 2029.

0%25%50%75%100%20252026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

21 September 2026

38%+8.2 pts

  • Skyscape construction site, inspection photo 1, 21 September 2026
  • Skyscape construction site, inspection photo 2, 21 September 2026
  • Skyscape construction site, inspection photo 3, 21 September 2026
  • Skyscape construction site, inspection photo 4, 21 September 2026

16 June 2026

30%+6.9 pts

  • Skyscape construction site, inspection photo 1, 16 June 2026
  • Skyscape construction site, inspection photo 2, 16 June 2026
  • Skyscape construction site, inspection photo 3, 16 June 2026
  • Skyscape construction site, inspection photo 4, 16 June 2026

31 March 2026

23%+11 pts

  • Skyscape construction site, inspection photo 1, 31 March 2026
  • Skyscape construction site, inspection photo 2, 31 March 2026
  • Skyscape construction site, inspection photo 3, 31 March 2026
  • Skyscape construction site, inspection photo 4, 31 March 2026

4 July 2025

12%+12 pts

  • Skyscape construction site, inspection photo 1, 4 July 2025
  • Skyscape construction site, inspection photo 2, 4 July 2025
  • Skyscape construction site, inspection photo 3, 4 July 2025
  • Skyscape construction site, inspection photo 4, 4 July 2025

22 July 2024

0%

  • Skyscape construction site, inspection photo 1, 22 July 2024
  • Skyscape construction site, inspection photo 2, 22 July 2024
  • Skyscape construction site, inspection photo 3, 22 July 2024

All 44 site photos, by inspection date

Context

Bukadra has 21 projects under construction, 27% built on average.

Sobha has 27 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Skyscape?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Skyscape handover date?
The registered completion date is December 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Skyscape?
Skyscape was 38% built at the site inspection on 21 September 2026. The site has been inspected 5 times since July 2024. The Land Department took 44 site photos at its inspections.
Is Skyscape delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2029.
Who is building Skyscape?
The registered developer is Sobha. It has 26 other projects under construction in Dubai.
Which bank holds the escrow account for Skyscape?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.