Belmore Residences construction progress
Belmore Residences in Bukadra is 6.5% built at the Land Department inspection of August 2026. Developer Ellington Properties Development. Completion registered for December 2027.
6.5%
Built, at the Land Department site inspection of 6 August 2026
Running behind its date
- Completion date (Land Department)
- December 2027
- Finish at recent pace
- September 2040
- Construction started
- August 2025
- Registered with the Land Department
- August 2025
- Developer
- Ellington Properties Development
- Community
- Bukadra
- Units
- 214
- Escrow bank
- Arab Bank
- Name in Arabic
- بيلمور ريزيدنسز
- Land Department project number
- 4033
- Land Department site inspections
- 3
Schedule
Between August 2025 and August 2026 the site added about 0.6 points a month. At that rate it would finish around September 2040, more than three months after the December 2027 date registered with the Land Department.
Site inspections
6 August 2026
6.5%+3.4 pts
25 March 2026
3.2%+3.0 pts
20 August 2025
0.2%
Context
Bukadra has 21 projects under construction, 26% built on average. Belmore Residences is behind that average.
Ellington Properties Development has 18 projects under construction in Dubai; 6 have passed their registered completion date.
Own a unit in Belmore Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Belmore Residences be completed?
- The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around September 2040. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Belmore Residences is built?
- 6.5%, measured at the Land Department site inspection on 6 August 2026. The Land Department engineers have inspected the site 3 times since August 2025.
- Is Belmore Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building Belmore Residences?
- The registered developer is Ellington Properties Development. It has 17 other projects under construction in Dubai.
- Which bank holds the escrow account for Belmore Residences?
- Arab Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The PortmanAlso by Ellington Properties Development. 79%, Due September 2025, passed.
- The HighburyAlso by Ellington Properties Development. 80%.
- Uh West By EllingtonAlso by Ellington Properties Development. 71%, Due March 2026, passed.
- Uh East By EllingtonAlso by Ellington Properties Development. 47%, Due March 2026, passed.
- 330 Riverside CrescentNearby in Bukadra. 60%.
- Sobha EstatesNearby in Bukadra. 68%, Due December 2027.
- 310 Riverside CrescentNearby in Bukadra. 50%.
- 360 Riverside CrescentNearby in Bukadra. 51%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.