Belmore Residences construction progress

Belmore Residences in Bukadra is 6.5% built at the Land Department inspection of August 2026. Developer Ellington Properties Development. Completion registered for December 2027.

6.5%

Built, at the Land Department site inspection of 6 August 2026

Running behind its date

Completion date (Land Department)
December 2027
Finish at recent pace
September 2040
Construction started
August 2025
Registered with the Land Department
August 2025
Community
Bukadra
Units
214
Escrow bank
Arab Bank
Name in Arabic
بيلمور ريزيدنسز
Land Department project number
4033
Land Department site inspections
3

Schedule

Between August 2025 and August 2026 the site added about 0.6 points a month. At that rate it would finish around September 2040, more than three months after the December 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

6 August 2026

6.5%+3.4 pts

  • Belmore Residences construction site, Land Department inspection photo 1, 6 August 2026
  • Belmore Residences construction site, Land Department inspection photo 2, 6 August 2026
  • Belmore Residences construction site, Land Department inspection photo 3, 6 August 2026
  • Belmore Residences construction site, Land Department inspection photo 4, 6 August 2026

25 March 2026

3.2%+3.0 pts

  • Belmore Residences construction site, Land Department inspection photo 1, 25 March 2026
  • Belmore Residences construction site, Land Department inspection photo 2, 25 March 2026
  • Belmore Residences construction site, Land Department inspection photo 3, 25 March 2026
  • Belmore Residences construction site, Land Department inspection photo 4, 25 March 2026

20 August 2025

0.2%

  • Belmore Residences construction site, Land Department inspection photo 1, 20 August 2025
  • Belmore Residences construction site, Land Department inspection photo 2, 20 August 2025
  • Belmore Residences construction site, Land Department inspection photo 3, 20 August 2025

All 11 site photos, by inspection date

Context

Bukadra has 21 projects under construction, 26% built on average. Belmore Residences is behind that average.

Ellington Properties Development has 18 projects under construction in Dubai; 6 have passed their registered completion date.

Own a unit in Belmore Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Belmore Residences be completed?
The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around September 2040. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Belmore Residences is built?
6.5%, measured at the Land Department site inspection on 6 August 2026. The Land Department engineers have inspected the site 3 times since August 2025.
Is Belmore Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Belmore Residences?
The registered developer is Ellington Properties Development. It has 17 other projects under construction in Dubai.
Which bank holds the escrow account for Belmore Residences?
Arab Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.