310 Riverside Crescent construction progress
No completion date is registered for 310 Riverside Crescent in Bukadra yet. At the last site inspection, in September 2026, it was 50% built. The developer is Sobha.
50%
Built, at the site inspection of 9 September 2026
Schedule
Since November 2025 310 Riverside Crescent has added about 2.1 points a month. At that rate the site reaches 100% around September 2028. No completion date is on record to compare it with.
Site inspections
9 September 2026
50%+5.7 pts
10 June 2026
45%+6.4 pts
12 March 2026
38%+8.6 pts
10 November 2025
29%+7.5 pts
9 May 2025
22%+4.9 pts
11 February 2025
17%+7.3 pts
5 November 2024
9.8%+9.8 pts
14 May 2024
0%
Context
Bukadra has 21 projects under construction, 27% built on average.
Sobha has 27 projects under construction in Dubai, none past their registered completion dates.
Own a unit in 310 Riverside Crescent?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the 310 Riverside Crescent handover date?
- No completion date is on record for 310 Riverside Crescent yet. Handover follows completion, so there is no date to give.
- What is the latest construction update on 310 Riverside Crescent?
- 310 Riverside Crescent was 50% built at the site inspection on 9 September 2026. The site has been inspected 8 times since May 2024. The Land Department took 51 site photos at its inspections.
- Who is building 310 Riverside Crescent?
- The registered developer is Sobha. It has 26 other projects under construction in Dubai.
- Which bank holds the escrow account for 310 Riverside Crescent?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sobha Seahaven Tower AAlso by Sobha. 45%, Due April 2028.
- Verde By SobhaAlso by Sobha. 85%, Due June 2027.
- Sobha Creek Vista HeightsAlso by Sobha. 92%.
- Sobha Seahaven Tower B & CAlso by Sobha. 40%, Due October 2028.
- Claydon House By EllingtonNearby in Bukadra. 16%, Due December 2027.
- The Waterway By Prestige OneNearby in Bukadra. 15%, Due June 2027.
- Parkway By Prestige OneNearby in Bukadra. 11%, Due January 2028.
- Ayaan Heights INearby in Bukadra. 20%, Due March 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)