Welcome Residency construction progress

The register lists Welcome Residency in Arjan as complete, with a registered completion date of June 2024. Its last site inspection on record was in September 2023. The developer is Alseeb Real Estate Development.

100%

Built, at the site inspection of 27 September 2023

Construction complete

Registered completion date
June 2024
Construction started
October 2021
First registered
May 2022
Community
Arjan
Units
94
Escrow bank
Dubai Islamic Bank
Name in Arabic
ويلكم ريزيدنسي
Project number
2360
Site inspections
6

Schedule

The register lists Welcome Residency as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202220232024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 September 2023

100%+10.0 pts

  • Welcome Residency construction site, inspection photo 1, 27 September 2023
  • Welcome Residency construction site, inspection photo 2, 27 September 2023
  • Welcome Residency construction site, inspection photo 3, 27 September 2023
  • Welcome Residency construction site, inspection photo 4, 27 September 2023

1 June 2023

90%+20 pts

  • Welcome Residency construction site, inspection photo 1, 1 June 2023
  • Welcome Residency construction site, inspection photo 2, 1 June 2023
  • Welcome Residency construction site, inspection photo 3, 1 June 2023
  • Welcome Residency construction site, inspection photo 4, 1 June 2023

15 February 2023

70%+20 pts

  • Welcome Residency construction site, inspection photo 1, 15 February 2023
  • Welcome Residency construction site, inspection photo 2, 15 February 2023
  • Welcome Residency construction site, inspection photo 3, 15 February 2023
  • Welcome Residency construction site, inspection photo 4, 15 February 2023

8 November 2022

50%+12 pts

  • Welcome Residency construction site, inspection photo 1, 8 November 2022
  • Welcome Residency construction site, inspection photo 2, 8 November 2022
  • Welcome Residency construction site, inspection photo 3, 8 November 2022
  • Welcome Residency construction site, inspection photo 4, 8 November 2022

22 August 2022

38%+29 pts

  • Welcome Residency construction site, inspection photo 1, 22 August 2022
  • Welcome Residency construction site, inspection photo 2, 22 August 2022
  • Welcome Residency construction site, inspection photo 3, 22 August 2022
  • Welcome Residency construction site, inspection photo 4, 22 August 2022

28 February 2022

9.6%

  • Welcome Residency construction site, inspection photo 1, 28 February 2022
  • Welcome Residency construction site, inspection photo 2, 28 February 2022
  • Welcome Residency construction site, inspection photo 3, 28 February 2022
  • Welcome Residency construction site, inspection photo 4, 28 February 2022

All 70 site photos, by inspection date

Context

Arjan has 23 projects under construction, 48% built on average.

Alseeb Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Welcome Residency?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Welcome Residency handover date?
Construction of Welcome Residency is recorded as complete, with a registered completion date of June 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Welcome Residency?
Welcome Residency was 100% built at the site inspection on 27 September 2023. The site has been inspected 6 times since February 2022. The Land Department took 70 site photos at its inspections.
Is Welcome Residency delayed?
The register lists construction as complete.
Who is building Welcome Residency?
The registered developer is Alseeb Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Welcome Residency?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.