Vincitore Wellness Estate construction progress

Vincitore Wellness Estate is 0% built at the Land Department inspection of July 2026. Developer Vincitore Premium Real Estate Development. Completion registered for February 2030.

0%

Built, at the Land Department site inspection of 14 July 2026

Running behind its date

Completion date (Land Department)
February 2030
Construction started
December 2025
Registered with the Land Department
December 2025
Units
1,475
Escrow bank
Mashreq Bank
Name in Arabic
فينسيتور ويلنس ستيت
Land Department project number
4148
Land Department site inspections
2

Schedule

0%25%50%75%100%20262027202820292030
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

14 July 2026

0%

  • Vincitore Wellness Estate construction site, Land Department inspection photo 1, 14 July 2026
  • Vincitore Wellness Estate construction site, Land Department inspection photo 2, 14 July 2026
  • Vincitore Wellness Estate construction site, Land Department inspection photo 3, 14 July 2026

28 October 2025

0%

  • Vincitore Wellness Estate construction site, Land Department inspection photo 1, 28 October 2025
  • Vincitore Wellness Estate construction site, Land Department inspection photo 2, 28 October 2025

All 5 site photos, by inspection date

Context

Vincitore Premium Real Estate Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Vincitore Wellness Estate?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Vincitore Wellness Estate be completed?
The completion date registered with the Dubai Land Department is February 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Vincitore Wellness Estate is built?
0%, measured at the Land Department site inspection on 14 July 2026. The Land Department engineers have inspected the site 2 times since October 2025.
Is Vincitore Wellness Estate delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2030.
Who is building Vincitore Wellness Estate?
The registered developer is Vincitore Premium Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Vincitore Wellness Estate?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.