Miraclz Tower construction progress

The register lists Miraclz Tower in Arjan as complete, with a registered completion date of April 2021. Its last site inspection on record was in April 2021. The developer is Danube Properties Development.

100%

Built, at the site inspection of 5 April 2021

Construction complete

Registered completion date
April 2021
Construction started
November 2016
First registered
October 2016
Community
Arjan
Units
599
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
ميراكلز تاور
Project number
1819
Site inspections
13

Schedule

The register lists Miraclz Tower as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20172018201920202021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 April 2021

100%+15 pts

  • Miraclz Tower construction site, inspection photo 1, 5 April 2021
  • Miraclz Tower construction site, inspection photo 2, 5 April 2021
  • Miraclz Tower construction site, inspection photo 3, 5 April 2021
  • Miraclz Tower construction site, inspection photo 4, 5 April 2021

6 January 2021

85%+11 pts

  • Miraclz Tower construction site, inspection photo 1, 6 January 2021
  • Miraclz Tower construction site, inspection photo 2, 6 January 2021
  • Miraclz Tower construction site, inspection photo 3, 6 January 2021
  • Miraclz Tower construction site, inspection photo 4, 6 January 2021

24 September 2020

74%+5.9 pts

  • Miraclz Tower construction site, inspection photo 1, 24 September 2020
  • Miraclz Tower construction site, inspection photo 2, 24 September 2020
  • Miraclz Tower construction site, inspection photo 3, 24 September 2020
  • Miraclz Tower construction site, inspection photo 4, 24 September 2020

3 June 2020

68%+18 pts

  • Miraclz Tower construction site, inspection photo 1, 3 June 2020
  • Miraclz Tower construction site, inspection photo 2, 3 June 2020
  • Miraclz Tower construction site, inspection photo 3, 3 June 2020
  • Miraclz Tower construction site, inspection photo 4, 3 June 2020

14 January 2020

50%+10 pts

  • Miraclz Tower construction site, inspection photo 1, 14 January 2020
  • Miraclz Tower construction site, inspection photo 2, 14 January 2020
  • Miraclz Tower construction site, inspection photo 3, 14 January 2020
  • Miraclz Tower construction site, inspection photo 4, 14 January 2020

15 September 2019

40%+7.6 pts

  • Miraclz Tower construction site, inspection photo 1, 15 September 2019
  • Miraclz Tower construction site, inspection photo 2, 15 September 2019
  • Miraclz Tower construction site, inspection photo 3, 15 September 2019
  • Miraclz Tower construction site, inspection photo 4, 15 September 2019

17 June 2019

33%+8.0 pts

  • Miraclz Tower construction site, inspection photo 1, 17 June 2019
  • Miraclz Tower construction site, inspection photo 2, 17 June 2019
  • Miraclz Tower construction site, inspection photo 3, 17 June 2019
  • Miraclz Tower construction site, inspection photo 4, 17 June 2019

6 February 2019

25%+4.6 pts

  • Miraclz Tower construction site, inspection photo 1, 6 February 2019
  • Miraclz Tower construction site, inspection photo 2, 6 February 2019
  • Miraclz Tower construction site, inspection photo 3, 6 February 2019
  • Miraclz Tower construction site, inspection photo 4, 6 February 2019

31 October 2018

20%+4.1 pts

  • Miraclz Tower construction site, inspection photo 1, 31 October 2018
  • Miraclz Tower construction site, inspection photo 2, 31 October 2018
  • Miraclz Tower construction site, inspection photo 3, 31 October 2018
  • Miraclz Tower construction site, inspection photo 4, 31 October 2018

25 July 2018

16%+4.6 pts

  • Miraclz Tower construction site, inspection photo 1, 25 July 2018
  • Miraclz Tower construction site, inspection photo 2, 25 July 2018
  • Miraclz Tower construction site, inspection photo 3, 25 July 2018

All 107 site photos, by inspection date

Context

Arjan has 23 projects under construction, 48% built on average.

Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.

Own a unit in Miraclz Tower?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Miraclz Tower handover date?
Construction of Miraclz Tower is recorded as complete, with a registered completion date of April 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Miraclz Tower?
Miraclz Tower was 100% built at the site inspection on 5 April 2021. The site has been inspected 13 times since August 2017. The Land Department took 107 site photos at its inspections.
Is Miraclz Tower delayed?
The register lists construction as complete.
Who is building Miraclz Tower?
The registered developer is Danube Properties Development. It has 23 other projects under construction in Dubai.
Which bank holds the escrow account for Miraclz Tower?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.