Marquis Galleria construction progress

The register lists Marquis Galleria in Arjan as complete, with a registered completion date of December 2024. Its last site inspection on record was in April 2026. The developer is Marquis Home Developer.

100%

Built, at the site inspection of 7 April 2026

Construction complete

Registered completion date
December 2024
Construction started
February 2023
First registered
April 2023
Community
Arjan
Units
126
Escrow bank
Emirates Islamic Bank
Name in Arabic
ماركيز جاليريا
Project number
2591
Site inspections
6

Schedule

The register lists Marquis Galleria as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

7 April 2026

100%+20 pts

  • Marquis Galleria construction site, inspection photo 1, 7 April 2026
  • Marquis Galleria construction site, inspection photo 2, 7 April 2026
  • Marquis Galleria construction site, inspection photo 3, 7 April 2026
  • Marquis Galleria construction site, inspection photo 4, 7 April 2026

16 July 2025

80%+5.8 pts

  • Marquis Galleria construction site, inspection photo 1, 16 July 2025
  • Marquis Galleria construction site, inspection photo 2, 16 July 2025
  • Marquis Galleria construction site, inspection photo 3, 16 July 2025
  • Marquis Galleria construction site, inspection photo 4, 16 July 2025

19 March 2025

74%+12 pts

  • Marquis Galleria construction site, inspection photo 1, 19 March 2025
  • Marquis Galleria construction site, inspection photo 2, 19 March 2025
  • Marquis Galleria construction site, inspection photo 3, 19 March 2025
  • Marquis Galleria construction site, inspection photo 4, 19 March 2025

18 December 2024

62%+26 pts

  • Marquis Galleria construction site, inspection photo 1, 18 December 2024
  • Marquis Galleria construction site, inspection photo 2, 18 December 2024
  • Marquis Galleria construction site, inspection photo 3, 18 December 2024
  • Marquis Galleria construction site, inspection photo 4, 18 December 2024

13 March 2024

36%+36 pts

  • Marquis Galleria construction site, inspection photo 1, 13 March 2024
  • Marquis Galleria construction site, inspection photo 2, 13 March 2024
  • Marquis Galleria construction site, inspection photo 3, 13 March 2024
  • Marquis Galleria construction site, inspection photo 4, 13 March 2024

27 February 2023

0.2%

  • Marquis Galleria construction site, inspection photo 1, 27 February 2023
  • Marquis Galleria construction site, inspection photo 2, 27 February 2023
  • Marquis Galleria construction site, inspection photo 3, 27 February 2023
  • Marquis Galleria construction site, inspection photo 4, 27 February 2023

All 55 site photos, by inspection date

Context

Arjan has 23 projects under construction, 48% built on average.

Marquis Home Developer has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Marquis Galleria?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Marquis Galleria handover date?
Construction of Marquis Galleria is recorded as complete, with a registered completion date of December 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Marquis Galleria?
Marquis Galleria was 100% built at the site inspection on 7 April 2026. The site has been inspected 6 times since February 2023. The Land Department took 55 site photos at its inspections.
Is Marquis Galleria delayed?
The register lists construction as complete.
Who is building Marquis Galleria?
The registered developer is Marquis Home Developer. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Marquis Galleria?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.