Skip to content

Marquis Vista construction progress

The registered completion date for Marquis Vista in Dubai Land Residence Complex is December 2027. At the last site inspection, in October 2026, it was 3.5% built. The developer is Marquis Home Developer.

3.5%

Built, at the site inspection of 19 October 2026

Running behind its date

Registered completion date
December 2027
Finish at recent pace
April 2043
Construction started
June 2025
First registered
July 2025
Units
129
Escrow bank
The National Bank of Fujairah
Name in Arabic
ماركيز فيستا
Project number
3632
Site inspections
4

Schedule

Between March 2026 and October 2026 the site added about 0.5 points a month. At that rate it would finish around April 2043, more than three months after its registered date of December 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

19 October 2026

3.5%+2.8 pts

  • Marquis Vista construction site, inspection photo 1, 19 October 2026
  • Marquis Vista construction site, inspection photo 2, 19 October 2026
  • Marquis Vista construction site, inspection photo 3, 19 October 2026
  • Marquis Vista construction site, inspection photo 4, 19 October 2026

1 July 2026

0.6%+0.6 pts

  • Marquis Vista construction site, inspection photo 1, 1 July 2026
  • Marquis Vista construction site, inspection photo 2, 1 July 2026
  • Marquis Vista construction site, inspection photo 3, 1 July 2026
  • Marquis Vista construction site, inspection photo 4, 1 July 2026

16 March 2026

0%

  • Marquis Vista construction site, inspection photo 1, 16 March 2026

22 April 2025

0%

  • Marquis Vista construction site, inspection photo 1, 22 April 2025
  • Marquis Vista construction site, inspection photo 2, 22 April 2025

All 12 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Marquis Home Developer has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Marquis Vista?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Marquis Vista handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2043. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Marquis Vista?
Marquis Vista was 3.5% built at the site inspection on 19 October 2026. The site has been inspected 4 times since April 2025. The Land Department took 12 site photos at its inspections.
Is Marquis Vista delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Marquis Vista?
The registered developer is Marquis Home Developer. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Marquis Vista?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.