Marquis Vista construction progress
Marquis Vista in Dubai Land Residence Complex is 0.6% built at the Land Department inspection of July 2026. Developer Marquis Home Developer. Completion registered for December 2027.
0.6%
Built, at the Land Department site inspection of 1 July 2026
Running behind its date
- Completion date (Land Department)
- December 2027
- Finish at recent pace
- December 2071
- Construction started
- June 2025
- Registered with the Land Department
- July 2025
- Developer
- Marquis Home Developer
- Community
- Dubai Land Residence Complex
- Units
- 129
- Escrow bank
- The National Bank of Fujairah
- Name in Arabic
- ماركيز فيستا
- Land Department project number
- 3632
- Land Department site inspections
- 3
Schedule
Between March 2026 and July 2026 the site added about 0.2 points a month. At that rate it would finish around December 2071, more than three months after the December 2027 date registered with the Land Department.
Site inspections
1 July 2026
0.6%+0.6 pts
16 March 2026
0%
22 April 2025
0%
Context
Dubai Land Residence Complex has 65 projects under construction, 24% built on average.
Marquis Home Developer has 3 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Marquis Vista?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Marquis Vista be completed?
- The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around December 2071. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Marquis Vista is built?
- 0.6%, measured at the Land Department site inspection on 1 July 2026. The Land Department engineers have inspected the site 3 times since April 2025.
- Is Marquis Vista delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building Marquis Vista?
- The registered developer is Marquis Home Developer. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Marquis Vista?
- The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Marquis OneAlso by Marquis Home Developer. 0%, Due December 2028.
- Marquis HorizonAlso by Marquis Home Developer. 0%.
- Ag CentralNearby in Dubai Land Residence Complex. 59%, Due October 2026.
- Ag SquareNearby in Dubai Land Residence Complex. 69%.
- Time 2Nearby in Dubai Land Residence Complex. 87%, Due June 2026, passed.
- Ag 7evenNearby in Dubai Land Residence Complex. 94%, Due March 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.