Jewelz Residence construction progress

The register lists Jewelz Residence in Arjan as complete, with a registered completion date of October 2023. Its last site inspection on record was in October 2023. The developer is Danube Properties Development.

100%

Built, at the site inspection of 30 October 2023

Construction complete

Registered completion date
October 2023
Construction started
March 2018
First registered
March 2018
Community
Arjan
Units
463
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
جويلز رزيدنس
Project number
2027
Site inspections
14

Schedule

The register lists Jewelz Residence as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20192020202120222023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 October 2023

100%+1.9 pts

  • Jewelz Residence construction site, inspection photo 1, 30 October 2023
  • Jewelz Residence construction site, inspection photo 2, 30 October 2023
  • Jewelz Residence construction site, inspection photo 3, 30 October 2023
  • Jewelz Residence construction site, inspection photo 4, 30 October 2023

26 September 2023

98%+9.9 pts

  • Jewelz Residence construction site, inspection photo 1, 26 September 2023
  • Jewelz Residence construction site, inspection photo 2, 26 September 2023
  • Jewelz Residence construction site, inspection photo 3, 26 September 2023
  • Jewelz Residence construction site, inspection photo 4, 26 September 2023

8 May 2023

88%+36 pts

  • Jewelz Residence construction site, inspection photo 1, 8 May 2023
  • Jewelz Residence construction site, inspection photo 2, 8 May 2023
  • Jewelz Residence construction site, inspection photo 3, 8 May 2023
  • Jewelz Residence construction site, inspection photo 4, 8 May 2023

18 January 2023

53%+7.6 pts

  • Jewelz Residence construction site, inspection photo 1, 18 January 2023
  • Jewelz Residence construction site, inspection photo 2, 18 January 2023
  • Jewelz Residence construction site, inspection photo 3, 18 January 2023
  • Jewelz Residence construction site, inspection photo 4, 18 January 2023

15 November 2022

45%+9.4 pts

  • Jewelz Residence construction site, inspection photo 1, 15 November 2022
  • Jewelz Residence construction site, inspection photo 2, 15 November 2022
  • Jewelz Residence construction site, inspection photo 3, 15 November 2022
  • Jewelz Residence construction site, inspection photo 4, 15 November 2022

25 July 2022

36%+4.8 pts

  • Jewelz Residence construction site, inspection photo 1, 25 July 2022
  • Jewelz Residence construction site, inspection photo 2, 25 July 2022
  • Jewelz Residence construction site, inspection photo 3, 25 July 2022
  • Jewelz Residence construction site, inspection photo 4, 25 July 2022

26 October 2021

31%

  • Jewelz Residence construction site, inspection photo 1, 26 October 2021
  • Jewelz Residence construction site, inspection photo 2, 26 October 2021
  • Jewelz Residence construction site, inspection photo 3, 26 October 2021
  • Jewelz Residence construction site, inspection photo 4, 26 October 2021

22 October 2020

32%+0.3 pts

  • Jewelz Residence construction site, inspection photo 1, 22 October 2020
  • Jewelz Residence construction site, inspection photo 2, 22 October 2020
  • Jewelz Residence construction site, inspection photo 3, 22 October 2020
  • Jewelz Residence construction site, inspection photo 4, 22 October 2020

3 June 2020

32%+0.1 pts

  • Jewelz Residence construction site, inspection photo 1, 3 June 2020
  • Jewelz Residence construction site, inspection photo 2, 3 June 2020
  • Jewelz Residence construction site, inspection photo 3, 3 June 2020
  • Jewelz Residence construction site, inspection photo 4, 3 June 2020

13 January 2020

31%+9.0 pts

  • Jewelz Residence construction site, inspection photo 1, 13 January 2020
  • Jewelz Residence construction site, inspection photo 2, 13 January 2020
  • Jewelz Residence construction site, inspection photo 3, 13 January 2020
  • Jewelz Residence construction site, inspection photo 4, 13 January 2020

All 130 site photos, by inspection date

Context

Arjan has 23 projects under construction, 48% built on average.

Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.

Own a unit in Jewelz Residence?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Jewelz Residence handover date?
Construction of Jewelz Residence is recorded as complete, with a registered completion date of October 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Jewelz Residence?
Jewelz Residence was 100% built at the site inspection on 30 October 2023. The site has been inspected 14 times since September 2018. The Land Department took 130 site photos at its inspections.
Is Jewelz Residence delayed?
The register lists construction as complete.
Who is building Jewelz Residence?
The registered developer is Danube Properties Development. It has 23 other projects under construction in Dubai.
Which bank holds the escrow account for Jewelz Residence?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.