Genesis construction progress

The register lists Genesis in Arjan as complete, with a registered completion date of February 2020. Its last site inspection on record was in February 2020. The developer is Meraki Real Estate Development.

100%

Built, at the site inspection of 25 February 2020

Construction complete

Registered completion date
February 2020
Construction started
September 2017
First registered
April 2018
Community
Arjan
Units
200
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
جينسيس
Project number
2044
Site inspections
6

Schedule

The register lists Genesis as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201820192020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

25 February 2020

100%+0.9 pts

  • Genesis construction site, inspection photo 1, 25 February 2020
  • Genesis construction site, inspection photo 2, 25 February 2020
  • Genesis construction site, inspection photo 3, 25 February 2020
  • Genesis construction site, inspection photo 4, 25 February 2020

12 February 2020

99%+19 pts

  • Genesis construction site, inspection photo 1, 12 February 2020
  • Genesis construction site, inspection photo 2, 12 February 2020
  • Genesis construction site, inspection photo 3, 12 February 2020
  • Genesis construction site, inspection photo 4, 12 February 2020

17 April 2019

80%+15 pts

  • Genesis construction site, inspection photo 1, 17 April 2019
  • Genesis construction site, inspection photo 2, 17 April 2019
  • Genesis construction site, inspection photo 3, 17 April 2019
  • Genesis construction site, inspection photo 4, 17 April 2019

21 January 2019

65%+20 pts

  • Genesis construction site, inspection photo 1, 21 January 2019
  • Genesis construction site, inspection photo 2, 21 January 2019
  • Genesis construction site, inspection photo 3, 21 January 2019
  • Genesis construction site, inspection photo 4, 21 January 2019

5 September 2018

45%+25 pts

  • Genesis construction site, inspection photo 1, 5 September 2018
  • Genesis construction site, inspection photo 2, 5 September 2018
  • Genesis construction site, inspection photo 3, 5 September 2018
  • Genesis construction site, inspection photo 4, 5 September 2018

2 April 2018

20%

  • Genesis construction site, inspection photo 1, 2 April 2018
  • Genesis construction site, inspection photo 2, 2 April 2018
  • Genesis construction site, inspection photo 3, 2 April 2018
  • Genesis construction site, inspection photo 4, 2 April 2018

All 61 site photos, by inspection date

Context

Arjan has 23 projects under construction, 48% built on average.

Meraki Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Genesis?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Genesis handover date?
Construction of Genesis is recorded as complete, with a registered completion date of February 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Genesis?
Genesis was 100% built at the site inspection on 25 February 2020. The site has been inspected 6 times since April 2018. The Land Department took 61 site photos at its inspections.
Is Genesis delayed?
The register lists construction as complete.
Who is building Genesis?
The registered developer is Meraki Real Estate Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Genesis?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.