Skip to content

Nirvana Residences - I construction progress

The registered completion date for Nirvana Residences - I is December 2028. At the last site inspection, in August 2026, it was 0% built. The developer is Meraki Real Estate Development.

0%

Built, at the site inspection of 12 August 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
January 3566
Construction started
March 2026
First registered
February 2026
Units
326
Escrow bank
Dubai Islamic Bank
Name in Arabic
I-نيرفانا ريسيدنسس
Project number
4313
Site inspections
2

Schedule

Between December 2025 and August 2026 the site added about 0.0 points a month. At that rate it would finish around January 3566, more than three months after its registered date of December 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 August 2026

0%+0.0 pts

  • Nirvana Residences - I construction site, inspection photo 1, 12 August 2026
  • Nirvana Residences - I construction site, inspection photo 2, 12 August 2026
  • Nirvana Residences - I construction site, inspection photo 3, 12 August 2026

30 December 2025

0%

  • Nirvana Residences - I construction site, inspection photo 1, 30 December 2025
  • Nirvana Residences - I construction site, inspection photo 2, 30 December 2025

All 5 site photos, by inspection date

Context

Meraki Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Nirvana Residences - I?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Nirvana Residences - I handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 3566. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Nirvana Residences - I?
Nirvana Residences - I was 0% built at the site inspection on 12 August 2026. The site has been inspected 2 times since December 2025. The Land Department took 5 site photos at its inspections.
Is Nirvana Residences - I delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Nirvana Residences - I?
The registered developer is Meraki Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Nirvana Residences - I?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.