Nirvana Residences - I construction progress

Nirvana Residences - I is 0% built at the Land Department inspection of August 2026. Developer Meraki Real Estate Development. Completion registered for December 2028.

0%

Built, at the Land Department site inspection of 12 August 2026

Running behind its date

Completion date (Land Department)
December 2028
Finish at recent pace
January 3566
Construction started
March 2026
Registered with the Land Department
February 2026
Units
326
Escrow bank
Dubai Islamic Bank
Name in Arabic
I-نيرفانا ريسيدنسس
Land Department project number
4313
Land Department site inspections
2

Schedule

Between December 2025 and August 2026 the site added about 0.0 points a month. At that rate it would finish around January 3566, more than three months after the December 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

12 August 2026

0%+0.0 pts

  • Nirvana Residences - I construction site, Land Department inspection photo 1, 12 August 2026
  • Nirvana Residences - I construction site, Land Department inspection photo 2, 12 August 2026
  • Nirvana Residences - I construction site, Land Department inspection photo 3, 12 August 2026

30 December 2025

0%

  • Nirvana Residences - I construction site, Land Department inspection photo 1, 30 December 2025
  • Nirvana Residences - I construction site, Land Department inspection photo 2, 30 December 2025

All 5 site photos, by inspection date

Context

Meraki Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Nirvana Residences - I?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Nirvana Residences - I be completed?
The completion date registered with the Dubai Land Department is December 2028. At the pace of its recent inspections the site would reach 100% around January 3566. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Nirvana Residences - I is built?
0%, measured at the Land Department site inspection on 12 August 2026. The Land Department engineers have inspected the site 2 times since December 2025.
Is Nirvana Residences - I delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Nirvana Residences - I?
The registered developer is Meraki Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Nirvana Residences - I?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.