The Haven II construction progress

The registered completion date for The Haven II in Majan is December 2026. At the last site inspection, in October 2026, it was 56% built. The developer is Meraki Real Estate Development.

56%

Built, at the site inspection of 14 October 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
October 2027
Construction started
August 2024
First registered
October 2024
Community
Majan
Units
225
Escrow bank
Dubai Islamic Bank
Name in Arabic
Iiذا هيفين
Project number
3315
Site inspections
7

Schedule

Between October 2025 and October 2026 the site added about 3.5 points a month. At that rate it would finish around October 2027, more than three months after its registered date of December 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 October 2026

56%+23 pts

  • The Haven II construction site, inspection photo 1, 14 October 2026
  • The Haven II construction site, inspection photo 2, 14 October 2026
  • The Haven II construction site, inspection photo 3, 14 October 2026
  • The Haven II construction site, inspection photo 4, 14 October 2026

22 June 2026

34%+12 pts

  • The Haven II construction site, inspection photo 1, 22 June 2026
  • The Haven II construction site, inspection photo 2, 22 June 2026
  • The Haven II construction site, inspection photo 3, 22 June 2026
  • The Haven II construction site, inspection photo 4, 22 June 2026

3 February 2026

22%+7.3 pts

  • The Haven II construction site, inspection photo 1, 3 February 2026
  • The Haven II construction site, inspection photo 2, 3 February 2026
  • The Haven II construction site, inspection photo 3, 3 February 2026
  • The Haven II construction site, inspection photo 4, 3 February 2026

20 October 2025

15%+11 pts

  • The Haven II construction site, inspection photo 1, 20 October 2025
  • The Haven II construction site, inspection photo 2, 20 October 2025
  • The Haven II construction site, inspection photo 3, 20 October 2025
  • The Haven II construction site, inspection photo 4, 20 October 2025

10 July 2025

3.8%+2.4 pts

  • The Haven II construction site, inspection photo 1, 10 July 2025
  • The Haven II construction site, inspection photo 2, 10 July 2025
  • The Haven II construction site, inspection photo 3, 10 July 2025
  • The Haven II construction site, inspection photo 4, 10 July 2025

9 June 2025

1.4%+1.4 pts

  • The Haven II construction site, inspection photo 1, 9 June 2025
  • The Haven II construction site, inspection photo 2, 9 June 2025
  • The Haven II construction site, inspection photo 3, 9 June 2025
  • The Haven II construction site, inspection photo 4, 9 June 2025

24 September 2024

0%

  • The Haven II construction site, inspection photo 1, 24 September 2024
  • The Haven II construction site, inspection photo 2, 24 September 2024

All 39 site photos, by inspection date

Context

Majan has 25 projects under construction, 28% built on average.

Meraki Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Haven II?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Haven II handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Haven II?
The Haven II was 56% built at the site inspection on 14 October 2026. The site has been inspected 7 times since September 2024. The Land Department took 39 site photos at its inspections.
Is The Haven II delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building The Haven II?
The registered developer is Meraki Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for The Haven II?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.