Skip to content

Elz Residence construction progress

The register lists Elz Residence in Arjan as complete, with a registered completion date of May 2022. Its last site inspection on record was in May 2022. The developer is Danube Properties Development.

100%

Built, at the site inspection of 23 May 2022

Construction complete

Registered completion date
May 2022
Construction started
January 2019
First registered
December 2018
Community
Arjan
Units
275
Escrow bank
First Abu Dhabi Bank
Name in Arabic
إلز رزيدنس
Project number
2115
Site inspections
11

Schedule

The register lists Elz Residence as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202020212022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

23 May 2022

100%+6.5 pts

  • Elz Residence construction site, inspection photo 1, 23 May 2022
  • Elz Residence construction site, inspection photo 2, 23 May 2022
  • Elz Residence construction site, inspection photo 3, 23 May 2022
  • Elz Residence construction site, inspection photo 4, 23 May 2022

3 February 2022

93%+16 pts

  • Elz Residence construction site, inspection photo 1, 3 February 2022
  • Elz Residence construction site, inspection photo 2, 3 February 2022
  • Elz Residence construction site, inspection photo 3, 3 February 2022
  • Elz Residence construction site, inspection photo 4, 3 February 2022

21 September 2021

78%+16 pts

  • Elz Residence construction site, inspection photo 1, 21 September 2021
  • Elz Residence construction site, inspection photo 2, 21 September 2021
  • Elz Residence construction site, inspection photo 3, 21 September 2021
  • Elz Residence construction site, inspection photo 4, 21 September 2021

15 June 2021

62%+14 pts

  • Elz Residence construction site, inspection photo 1, 15 June 2021
  • Elz Residence construction site, inspection photo 2, 15 June 2021
  • Elz Residence construction site, inspection photo 3, 15 June 2021
  • Elz Residence construction site, inspection photo 4, 15 June 2021

4 March 2021

47%+12 pts

  • Elz Residence construction site, inspection photo 1, 4 March 2021
  • Elz Residence construction site, inspection photo 2, 4 March 2021
  • Elz Residence construction site, inspection photo 3, 4 March 2021
  • Elz Residence construction site, inspection photo 4, 4 March 2021

18 November 2020

35%+15 pts

  • Elz Residence construction site, inspection photo 1, 18 November 2020
  • Elz Residence construction site, inspection photo 2, 18 November 2020
  • Elz Residence construction site, inspection photo 3, 18 November 2020
  • Elz Residence construction site, inspection photo 4, 18 November 2020

28 July 2020

20%+8.2 pts

  • Elz Residence construction site, inspection photo 1, 28 July 2020
  • Elz Residence construction site, inspection photo 2, 28 July 2020
  • Elz Residence construction site, inspection photo 3, 28 July 2020
  • Elz Residence construction site, inspection photo 4, 28 July 2020

28 April 2020

12%+10 pts

  • Elz Residence construction site, inspection photo 1, 28 April 2020
  • Elz Residence construction site, inspection photo 2, 28 April 2020
  • Elz Residence construction site, inspection photo 3, 28 April 2020
  • Elz Residence construction site, inspection photo 4, 28 April 2020

13 January 2020

1.7%

  • Elz Residence construction site, inspection photo 1, 13 January 2020
  • Elz Residence construction site, inspection photo 2, 13 January 2020
  • Elz Residence construction site, inspection photo 3, 13 January 2020
  • Elz Residence construction site, inspection photo 4, 13 January 2020

2 October 2019

2.2%+1.3 pts

  • Elz Residence construction site, inspection photo 1, 2 October 2019
  • Elz Residence construction site, inspection photo 2, 2 October 2019
  • Elz Residence construction site, inspection photo 3, 2 October 2019
  • Elz Residence construction site, inspection photo 4, 2 October 2019

All 100 site photos, by inspection date

Context

Arjan has 23 projects under construction, 48% built on average.

Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.

Own a unit in Elz Residence?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Elz Residence handover date?
Construction of Elz Residence is recorded as complete, with a registered completion date of May 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Elz Residence?
Elz Residence was 100% built at the site inspection on 23 May 2022. The site has been inspected 11 times since July 2019. The Land Department took 100 site photos at its inspections.
Is Elz Residence delayed?
The register lists construction as complete.
Who is building Elz Residence?
The registered developer is Danube Properties Development. It has 23 other projects under construction in Dubai.
Which bank holds the escrow account for Elz Residence?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.