Starz Tower By Danube construction progress
The register lists Starz Tower By Danube in Al Furjan as complete, with a registered completion date of February 2019. Its last site inspection on record was in May 2019. The developer is Danube Properties Development.
100%
Built, at the site inspection of 19 May 2019
Construction complete
- Registered completion date
- February 2019
- Construction started
- March 2016
- First registered
- December 2015
- Developer
- Danube Properties Development
- Community
- Al Furjan
- Units
- 454
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- ستارز تاور من الدانوب
- Project number
- 1699
- Site inspections
- 10
Schedule
The register lists Starz Tower By Danube as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
19 May 2019
100%+9.1 pts
17 February 2019
91%+10 pts
15 November 2018
81%+8.0 pts
17 September 2018
73%+12 pts
23 May 2018
61%+15 pts
4 February 2018
45%+22 pts
17 September 2017
24%+7.8 pts
21 May 2017
16%+13 pts
5 December 2016
2.8%+2.1 pts
22 August 2016
0.7%
Context
Al Furjan has 38 projects under construction, 32% built on average.
Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.
Own a unit in Starz Tower By Danube?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Starz Tower By Danube handover date?
- Construction of Starz Tower By Danube is recorded as complete, with a registered completion date of February 2019. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Starz Tower By Danube?
- Starz Tower By Danube was 100% built at the site inspection on 19 May 2019. The site has been inspected 10 times since August 2016. The Land Department took 85 site photos at its inspections.
- Is Starz Tower By Danube delayed?
- The register lists construction as complete.
- Who is building Starz Tower By Danube?
- The registered developer is Danube Properties Development. It has 23 other projects under construction in Dubai.
- Which bank holds the escrow account for Starz Tower By Danube?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Elitz By DanubeAlso by Danube Properties Development. 92%, Due December 2025, passed.
- Viewz 1 By DanubeAlso by Danube Properties Development. 66%, Due June 2026, passed.
- Viewz 2 By DanubeAlso by Danube Properties Development. 65%, Due June 2026, passed.
- Fashionz 1 By DanubeAlso by Danube Properties Development. 40%.
- Trussardi ResidencesNearby in Al Furjan. 36%, Due January 2026, passed.
- Rosalia ResidencesNearby in Al Furjan. 93%.
- The Stella ResidencesNearby in Al Furjan. 71%, Due December 2025, passed.
- Symbolic AuraNearby in Al Furjan. 70%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)