Dreamz construction progress

The register lists Dreamz in Al Furjan as complete, with a registered completion date of March 2018. Its last site inspection on record was in March 2018. The developer is Danube Properties Development.

100%

Built, at the site inspection of 20 March 2018

Construction complete

Registered completion date
March 2018
Construction started
September 2014
First registered
June 2014
Community
Al Furjan
Units
171
Escrow bank
Emirates Islamic Bank
Name in Arabic
دريمز
Project number
1534
Site inspections
8

Schedule

The register lists Dreamz as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2015201620172018
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 March 2018

100%+2.3 pts

  • Dreamz construction site, inspection photo 1, 20 March 2018
  • Dreamz construction site, inspection photo 2, 20 March 2018
  • Dreamz construction site, inspection photo 3, 20 March 2018
  • Dreamz construction site, inspection photo 4, 20 March 2018

7 January 2018

98%+1.3 pts

  • Dreamz construction site, inspection photo 1, 7 January 2018
  • Dreamz construction site, inspection photo 2, 7 January 2018
  • Dreamz construction site, inspection photo 3, 7 January 2018
  • Dreamz construction site, inspection photo 4, 7 January 2018

19 September 2017

96%+16 pts

  • Dreamz construction site, inspection photo 1, 19 September 2017
  • Dreamz construction site, inspection photo 2, 19 September 2017
  • Dreamz construction site, inspection photo 3, 19 September 2017
  • Dreamz construction site, inspection photo 4, 19 September 2017

11 January 2017

81%+15 pts

  • Dreamz construction site, inspection photo 1, 11 January 2017
  • Dreamz construction site, inspection photo 2, 11 January 2017
  • Dreamz construction site, inspection photo 3, 11 January 2017
  • Dreamz construction site, inspection photo 4, 11 January 2017

23 August 2016

66%+14 pts

  • Dreamz construction site, inspection photo 1, 23 August 2016
  • Dreamz construction site, inspection photo 2, 23 August 2016
  • Dreamz construction site, inspection photo 3, 23 August 2016
  • Dreamz construction site, inspection photo 4, 23 August 2016

4 May 2016

52%+20 pts

  • Dreamz construction site, inspection photo 1, 4 May 2016
  • Dreamz construction site, inspection photo 2, 4 May 2016
  • Dreamz construction site, inspection photo 3, 4 May 2016
  • Dreamz construction site, inspection photo 4, 4 May 2016

29 December 2015

32%+27 pts

  • Dreamz construction site, inspection photo 1, 29 December 2015
  • Dreamz construction site, inspection photo 2, 29 December 2015
  • Dreamz construction site, inspection photo 3, 29 December 2015
  • Dreamz construction site, inspection photo 4, 29 December 2015

10 March 2015

5.0%

  • Dreamz construction site, inspection photo 1, 10 March 2015
  • Dreamz construction site, inspection photo 2, 10 March 2015
  • Dreamz construction site, inspection photo 3, 10 March 2015

All 72 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.

Own a unit in Dreamz?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Dreamz handover date?
Construction of Dreamz is recorded as complete, with a registered completion date of March 2018. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Dreamz?
Dreamz was 100% built at the site inspection on 20 March 2018. The site has been inspected 8 times since March 2015. The Land Department took 72 site photos at its inspections.
Is Dreamz delayed?
The register lists construction as complete.
Who is building Dreamz?
The registered developer is Danube Properties Development. It has 23 other projects under construction in Dubai.
Which bank holds the escrow account for Dreamz?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.