Belle Reve By Zimaya construction progress

Belle Reve By Zimaya in Jumeirah Village Circle is 81% built at the Land Department inspection of September 2026. Developer Zimaya Properties. Completion registered for August 2026.

81%

Built, at the Land Department site inspection of 10 September 2026

1 months past its registered completion date

Completion date (Land Department)
August 2026
Finish at recent pace
February 2027
Construction started
June 2024
Registered with the Land Department
July 2024
Units
190
Escrow bank
Mashreq Bank
Name in Arabic
بيل ريف من زيمايا
Land Department project number
3027
Land Department site inspections
6

Schedule

Belle Reve By Zimaya was registered to complete in August 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 3.5 points a month. Kept at that rate, the site would reach 100% around February 2027.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

10 September 2026

81%+20 pts

  • Belle Reve By Zimaya construction site, Land Department inspection photo 1, 10 September 2026
  • Belle Reve By Zimaya construction site, Land Department inspection photo 2, 10 September 2026
  • Belle Reve By Zimaya construction site, Land Department inspection photo 3, 10 September 2026
  • Belle Reve By Zimaya construction site, Land Department inspection photo 4, 10 September 2026

13 April 2026

60%+15 pts

  • Belle Reve By Zimaya construction site, Land Department inspection photo 1, 13 April 2026
  • Belle Reve By Zimaya construction site, Land Department inspection photo 2, 13 April 2026
  • Belle Reve By Zimaya construction site, Land Department inspection photo 3, 13 April 2026
  • Belle Reve By Zimaya construction site, Land Department inspection photo 4, 13 April 2026

6 November 2025

45%+19 pts

  • Belle Reve By Zimaya construction site, Land Department inspection photo 1, 6 November 2025
  • Belle Reve By Zimaya construction site, Land Department inspection photo 2, 6 November 2025
  • Belle Reve By Zimaya construction site, Land Department inspection photo 3, 6 November 2025
  • Belle Reve By Zimaya construction site, Land Department inspection photo 4, 6 November 2025

12 June 2025

26%+14 pts

  • Belle Reve By Zimaya construction site, Land Department inspection photo 1, 12 June 2025
  • Belle Reve By Zimaya construction site, Land Department inspection photo 2, 12 June 2025
  • Belle Reve By Zimaya construction site, Land Department inspection photo 3, 12 June 2025
  • Belle Reve By Zimaya construction site, Land Department inspection photo 4, 12 June 2025

27 January 2025

12%+12 pts

  • Belle Reve By Zimaya construction site, Land Department inspection photo 1, 27 January 2025
  • Belle Reve By Zimaya construction site, Land Department inspection photo 2, 27 January 2025
  • Belle Reve By Zimaya construction site, Land Department inspection photo 3, 27 January 2025
  • Belle Reve By Zimaya construction site, Land Department inspection photo 4, 27 January 2025

17 April 2024

0%

  • Belle Reve By Zimaya construction site, Land Department inspection photo 1, 17 April 2024
  • Belle Reve By Zimaya construction site, Land Department inspection photo 2, 17 April 2024
  • Belle Reve By Zimaya construction site, Land Department inspection photo 3, 17 April 2024

All 49 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average. Belle Reve By Zimaya is ahead of that average.

Zimaya Properties has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Belle Reve By Zimaya?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Belle Reve By Zimaya be completed?
The completion date registered with the Dubai Land Department is August 2026. At the pace of its recent inspections the site would reach 100% around February 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Belle Reve By Zimaya is built?
81%, measured at the Land Department site inspection on 10 September 2026. The Land Department engineers have inspected the site 6 times since April 2024.
Is Belle Reve By Zimaya delayed?
Yes. Its registered completion date of August 2026 has passed and the Land Department still lists it as under construction.
Who is building Belle Reve By Zimaya?
The registered developer is Zimaya Properties. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Belle Reve By Zimaya?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.