Belle Reve By Zimaya construction progress
Belle Reve By Zimaya in Jumeirah Village Circle is 81% built at the Land Department inspection of September 2026. Developer Zimaya Properties. Completion registered for August 2026.
81%
Built, at the Land Department site inspection of 10 September 2026
1 months past its registered completion date
- Completion date (Land Department)
- August 2026
- Finish at recent pace
- February 2027
- Construction started
- June 2024
- Registered with the Land Department
- July 2024
- Developer
- Zimaya Properties
- Community
- Jumeirah Village Circle
- Units
- 190
- Escrow bank
- Mashreq Bank
- Name in Arabic
- بيل ريف من زيمايا
- Land Department project number
- 3027
- Land Department site inspections
- 6
Schedule
Belle Reve By Zimaya was registered to complete in August 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 3.5 points a month. Kept at that rate, the site would reach 100% around February 2027.
Site inspections
10 September 2026
81%+20 pts
13 April 2026
60%+15 pts
6 November 2025
45%+19 pts
12 June 2025
26%+14 pts
27 January 2025
12%+12 pts
17 April 2024
0%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average. Belle Reve By Zimaya is ahead of that average.
Zimaya Properties has 4 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Belle Reve By Zimaya?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Belle Reve By Zimaya be completed?
- The completion date registered with the Dubai Land Department is August 2026. At the pace of its recent inspections the site would reach 100% around February 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Belle Reve By Zimaya is built?
- 81%, measured at the Land Department site inspection on 10 September 2026. The Land Department engineers have inspected the site 6 times since April 2024.
- Is Belle Reve By Zimaya delayed?
- Yes. Its registered completion date of August 2026 has passed and the Land Department still lists it as under construction.
- Who is building Belle Reve By Zimaya?
- The registered developer is Zimaya Properties. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Belle Reve By Zimaya?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Celeste Heights By Zimaya PropertiesAlso by Zimaya Properties. 31%, Due September 2027.
- Belle Vie By ZimayaAlso by Zimaya Properties. 11%, Due March 2028.
- Lawncrest By ZimayaAlso by Zimaya Properties. 0%.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)