The Acres construction photos
61 photos taken by Dubai Land Department engineers at 8 site inspections, newest first. The percentage is how much of The Acres was built on the day of each visit.
20 August 202625% built
14 May 202615% built
23 February 20269.1% built
11 November 20251.6% built
3 October 20250.3% built
7 April 20250.3% built
25 November 20240.2% built
27 March 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.