La Quinta construction progress

The register lists La Quinta in Wadi Al Safa 5 as complete, with a registered completion date of July 2021. Its last site inspection on record was in August 2021. The developer is North Dubailand Projects.

100%

Built, at the site inspection of 15 August 2021

Construction complete

Registered completion date
July 2021
Construction started
April 2017
First registered
January 2017
Units
249
Escrow bank
Dubai Islamic Bank
Name in Arabic
لا كينتا
Project number
1851
Site inspections
8

Schedule

The register lists La Quinta as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2018201920202021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 August 2021

100%+8.8 pts

  • La Quinta construction site, inspection photo 1, 15 August 2021
  • La Quinta construction site, inspection photo 2, 15 August 2021
  • La Quinta construction site, inspection photo 3, 15 August 2021
  • La Quinta construction site, inspection photo 4, 15 August 2021

1 July 2020

91%+3.6 pts

  • La Quinta construction site, inspection photo 1, 1 July 2020
  • La Quinta construction site, inspection photo 2, 1 July 2020
  • La Quinta construction site, inspection photo 3, 1 July 2020
  • La Quinta construction site, inspection photo 4, 1 July 2020

16 March 2020

88%+19 pts

  • La Quinta construction site, inspection photo 1, 16 March 2020
  • La Quinta construction site, inspection photo 2, 16 March 2020
  • La Quinta construction site, inspection photo 3, 16 March 2020
  • La Quinta construction site, inspection photo 4, 16 March 2020

13 November 2019

68%+26 pts

  • La Quinta construction site, inspection photo 1, 13 November 2019
  • La Quinta construction site, inspection photo 2, 13 November 2019
  • La Quinta construction site, inspection photo 3, 13 November 2019
  • La Quinta construction site, inspection photo 4, 13 November 2019

8 July 2019

42%+26 pts

  • La Quinta construction site, inspection photo 1, 8 July 2019
  • La Quinta construction site, inspection photo 2, 8 July 2019
  • La Quinta construction site, inspection photo 3, 8 July 2019
  • La Quinta construction site, inspection photo 4, 8 July 2019

31 January 2019

16%+12 pts

  • La Quinta construction site, inspection photo 1, 31 January 2019
  • La Quinta construction site, inspection photo 2, 31 January 2019
  • La Quinta construction site, inspection photo 3, 31 January 2019
  • La Quinta construction site, inspection photo 4, 31 January 2019

20 September 2018

3.8%+2.0 pts

  • La Quinta construction site, inspection photo 1, 20 September 2018
  • La Quinta construction site, inspection photo 2, 20 September 2018
  • La Quinta construction site, inspection photo 3, 20 September 2018
  • La Quinta construction site, inspection photo 4, 20 September 2018

10 June 2018

1.8%

  • La Quinta construction site, inspection photo 1, 10 June 2018
  • La Quinta construction site, inspection photo 2, 10 June 2018
  • La Quinta construction site, inspection photo 3, 10 June 2018
  • La Quinta construction site, inspection photo 4, 10 June 2018

All 72 site photos, by inspection date

Context

Wadi Al Safa 5 has 13 projects under construction, 24% built on average.

North Dubailand Projects has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in La Quinta?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the La Quinta handover date?
Construction of La Quinta is recorded as complete, with a registered completion date of July 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on La Quinta?
La Quinta was 100% built at the site inspection on 15 August 2021. The site has been inspected 8 times since June 2018. The Land Department took 72 site photos at its inspections.
Is La Quinta delayed?
The register lists construction as complete.
Who is building La Quinta?
The registered developer is North Dubailand Projects. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for La Quinta?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.