La Quinta construction photos
72 photos from 8 site inspections, newest first. The percentage is how much of La Quinta was built on the day of each visit.
15 August 2021100% built
1 July 202091% built
16 March 202088% built
13 November 201968% built
8 July 201942% built
31 January 201916% built
20 September 20183.8% built
10 June 20181.8% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.