Amaranta 2 construction progress

The register lists Amaranta 2 in Wadi Al Safa 5 as complete, with a registered completion date of March 2022. Its last site inspection on record was in March 2022. The developer is North Dubailand Projects.

100%

Built, at the site inspection of 21 March 2022

Construction complete

Registered completion date
March 2022
Construction started
January 2018
First registered
January 2018
Units
352
Escrow bank
Dubai Islamic Bank
Name in Arabic
امارانتا 2
Project number
2017
Site inspections
10

Schedule

The register lists Amaranta 2 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2019202020212022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

21 March 2022

100%+3.4 pts

  • Amaranta 2 construction site, inspection photo 1, 21 March 2022
  • Amaranta 2 construction site, inspection photo 2, 21 March 2022
  • Amaranta 2 construction site, inspection photo 3, 21 March 2022
  • Amaranta 2 construction site, inspection photo 4, 21 March 2022

17 November 2021

97%+9.3 pts

  • Amaranta 2 construction site, inspection photo 1, 17 November 2021
  • Amaranta 2 construction site, inspection photo 2, 17 November 2021
  • Amaranta 2 construction site, inspection photo 3, 17 November 2021
  • Amaranta 2 construction site, inspection photo 4, 17 November 2021

27 October 2020

87%+17 pts

  • Amaranta 2 construction site, inspection photo 1, 27 October 2020
  • Amaranta 2 construction site, inspection photo 2, 27 October 2020
  • Amaranta 2 construction site, inspection photo 3, 27 October 2020
  • Amaranta 2 construction site, inspection photo 4, 27 October 2020

29 June 2020

70%+16 pts

  • Amaranta 2 construction site, inspection photo 1, 29 June 2020
  • Amaranta 2 construction site, inspection photo 2, 29 June 2020
  • Amaranta 2 construction site, inspection photo 3, 29 June 2020
  • Amaranta 2 construction site, inspection photo 4, 29 June 2020

16 March 2020

54%+21 pts

  • Amaranta 2 construction site, inspection photo 1, 16 March 2020
  • Amaranta 2 construction site, inspection photo 2, 16 March 2020
  • Amaranta 2 construction site, inspection photo 3, 16 March 2020
  • Amaranta 2 construction site, inspection photo 4, 16 March 2020

13 November 2019

33%+21 pts

  • Amaranta 2 construction site, inspection photo 1, 13 November 2019
  • Amaranta 2 construction site, inspection photo 2, 13 November 2019
  • Amaranta 2 construction site, inspection photo 3, 13 November 2019
  • Amaranta 2 construction site, inspection photo 4, 13 November 2019

8 July 2019

12%+6.2 pts

  • Amaranta 2 construction site, inspection photo 1, 8 July 2019
  • Amaranta 2 construction site, inspection photo 2, 8 July 2019
  • Amaranta 2 construction site, inspection photo 3, 8 July 2019
  • Amaranta 2 construction site, inspection photo 4, 8 July 2019

26 March 2019

6.2%+4.0 pts

  • Amaranta 2 construction site, inspection photo 1, 26 March 2019
  • Amaranta 2 construction site, inspection photo 2, 26 March 2019
  • Amaranta 2 construction site, inspection photo 3, 26 March 2019
  • Amaranta 2 construction site, inspection photo 4, 26 March 2019

28 November 2018

2.3%+1.4 pts

  • Amaranta 2 construction site, inspection photo 1, 28 November 2018
  • Amaranta 2 construction site, inspection photo 2, 28 November 2018
  • Amaranta 2 construction site, inspection photo 3, 28 November 2018
  • Amaranta 2 construction site, inspection photo 4, 28 November 2018

22 July 2018

0.8%

  • Amaranta 2 construction site, inspection photo 1, 22 July 2018
  • Amaranta 2 construction site, inspection photo 2, 22 July 2018
  • Amaranta 2 construction site, inspection photo 3, 22 July 2018
  • Amaranta 2 construction site, inspection photo 4, 22 July 2018

All 87 site photos, by inspection date

Context

Wadi Al Safa 5 has 13 projects under construction, 24% built on average.

North Dubailand Projects has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Amaranta 2?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Amaranta 2 handover date?
Construction of Amaranta 2 is recorded as complete, with a registered completion date of March 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Amaranta 2?
Amaranta 2 was 100% built at the site inspection on 21 March 2022. The site has been inspected 10 times since July 2018. The Land Department took 87 site photos at its inspections.
Is Amaranta 2 delayed?
The register lists construction as complete.
Who is building Amaranta 2?
The registered developer is North Dubailand Projects. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Amaranta 2?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.