Amaranta 2 construction photos

87 photos from 10 site inspections, newest first. The percentage is how much of Amaranta 2 was built on the day of each visit.

21 March 2022100% built

17 November 202197% built

27 October 202087% built

29 June 202070% built

16 March 202054% built

13 November 201933% built

8 July 201912% built

26 March 20196.2% built

28 November 20182.3% built

22 July 20180.8% built

Back to Amaranta 2 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.