Trump Tower construction progress
Trump Tower in Trade Center First is 3.8% built at the Land Department inspection of September 2026. Developer Dar Global Luxury Property Development S.o.c. Completion registered for December 2031.
3.8%
Built, at the Land Department site inspection of 10 September 2026
Running behind its date
- Completion date (Land Department)
- December 2031
- Finish at recent pace
- October 2045
- Construction started
- January 2026
- Registered with the Land Department
- April 2025
- Developer
- Dar Global Luxury Property Development S.o.c
- Community
- Trade Center First
- Units
- 574
- Escrow bank
- Emirates NBD
- Name in Arabic
- ترامب تاور
- Land Department project number
- 3691
- Land Department site inspections
- 4
Schedule
Between December 2025 and September 2026 the site added about 0.4 points a month. At that rate it would finish around October 2045, more than three months after the December 2031 date registered with the Land Department.
Site inspections
10 September 2026
3.8%+1.8 pts
27 April 2026
2.0%+2.0 pts
9 December 2025
0%+0.0 pts
16 April 2025
0%
Context
Trade Center First has 3 projects under construction, 4.4% built on average.
Own a unit in Trump Tower?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Trump Tower be completed?
- The completion date registered with the Dubai Land Department is December 2031. At the pace of its recent inspections the site would reach 100% around October 2045. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Trump Tower is built?
- 3.8%, measured at the Land Department site inspection on 10 September 2026. The Land Department engineers have inspected the site 4 times since April 2025.
- Is Trump Tower delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2031.
- Who is building Trump Tower?
- The registered developer is Dar Global Luxury Property Development S.o.c.
- Which bank holds the escrow account for Trump Tower?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.