Trump Tower construction progress

Trump Tower in Trade Center First is 3.8% built at the Land Department inspection of September 2026. Developer Dar Global Luxury Property Development S.o.c. Completion registered for December 2031.

3.8%

Built, at the Land Department site inspection of 10 September 2026

Running behind its date

Completion date (Land Department)
December 2031
Finish at recent pace
October 2045
Construction started
January 2026
Registered with the Land Department
April 2025
Developer
Dar Global Luxury Property Development S.o.c
Units
574
Escrow bank
Emirates NBD
Name in Arabic
ترامب تاور
Land Department project number
3691
Land Department site inspections
4

Schedule

Between December 2025 and September 2026 the site added about 0.4 points a month. At that rate it would finish around October 2045, more than three months after the December 2031 date registered with the Land Department.

0%25%50%75%100%202620282030
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

10 September 2026

3.8%+1.8 pts

  • Trump Tower construction site, Land Department inspection photo 1, 10 September 2026
  • Trump Tower construction site, Land Department inspection photo 2, 10 September 2026
  • Trump Tower construction site, Land Department inspection photo 3, 10 September 2026
  • Trump Tower construction site, Land Department inspection photo 4, 10 September 2026

27 April 2026

2.0%+2.0 pts

  • Trump Tower construction site, Land Department inspection photo 1, 27 April 2026
  • Trump Tower construction site, Land Department inspection photo 2, 27 April 2026
  • Trump Tower construction site, Land Department inspection photo 3, 27 April 2026
  • Trump Tower construction site, Land Department inspection photo 4, 27 April 2026

9 December 2025

0%+0.0 pts

  • Trump Tower construction site, Land Department inspection photo 1, 9 December 2025
  • Trump Tower construction site, Land Department inspection photo 2, 9 December 2025

16 April 2025

0%

  • Trump Tower construction site, Land Department inspection photo 1, 16 April 2025
  • Trump Tower construction site, Land Department inspection photo 2, 16 April 2025

All 14 site photos, by inspection date

Context

Trade Center First has 3 projects under construction, 4.4% built on average.

Own a unit in Trump Tower?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Trump Tower be completed?
The completion date registered with the Dubai Land Department is December 2031. At the pace of its recent inspections the site would reach 100% around October 2045. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Trump Tower is built?
3.8%, measured at the Land Department site inspection on 10 September 2026. The Land Department engineers have inspected the site 4 times since April 2025.
Is Trump Tower delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2031.
Who is building Trump Tower?
The registered developer is Dar Global Luxury Property Development S.o.c.
Which bank holds the escrow account for Trump Tower?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.