The S Tower construction progress

The register lists The S Tower in Site A as complete, with a registered completion date of June 2025. Its last site inspection on record was in May 2025. The developer is Sobha.

100%

Built, at the site inspection of 20 May 2025

Construction complete

Registered completion date
June 2025
Construction started
May 2021
First registered
October 2022
Developer
Sobha
Community
Site A
Units
95
Escrow bank
Mashreq Bank
Name in Arabic
ذا إس تاور
Project number
2408
Site inspections
8

Schedule

The register lists The S Tower as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2022202320242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 May 2025

100%+5.5 pts

  • The S Tower construction site, inspection photo 1, 20 May 2025
  • The S Tower construction site, inspection photo 2, 20 May 2025
  • The S Tower construction site, inspection photo 3, 20 May 2025
  • The S Tower construction site, inspection photo 4, 20 May 2025

10 February 2025

95%+12 pts

  • The S Tower construction site, inspection photo 1, 10 February 2025
  • The S Tower construction site, inspection photo 2, 10 February 2025
  • The S Tower construction site, inspection photo 3, 10 February 2025
  • The S Tower construction site, inspection photo 4, 10 February 2025

13 February 2024

82%+6.7 pts

  • The S Tower construction site, inspection photo 1, 13 February 2024
  • The S Tower construction site, inspection photo 2, 13 February 2024
  • The S Tower construction site, inspection photo 3, 13 February 2024
  • The S Tower construction site, inspection photo 4, 13 February 2024

27 July 2023

76%+15 pts

  • The S Tower construction site, inspection photo 1, 27 July 2023
  • The S Tower construction site, inspection photo 2, 27 July 2023
  • The S Tower construction site, inspection photo 3, 27 July 2023
  • The S Tower construction site, inspection photo 4, 27 July 2023

13 March 2023

61%+16 pts

  • The S Tower construction site, inspection photo 1, 13 March 2023
  • The S Tower construction site, inspection photo 2, 13 March 2023
  • The S Tower construction site, inspection photo 3, 13 March 2023
  • The S Tower construction site, inspection photo 4, 13 March 2023

5 December 2022

45%+13 pts

  • The S Tower construction site, inspection photo 1, 5 December 2022
  • The S Tower construction site, inspection photo 2, 5 December 2022
  • The S Tower construction site, inspection photo 3, 5 December 2022
  • The S Tower construction site, inspection photo 4, 5 December 2022

20 September 2022

32%+11 pts

  • The S Tower construction site, inspection photo 1, 20 September 2022
  • The S Tower construction site, inspection photo 2, 20 September 2022
  • The S Tower construction site, inspection photo 3, 20 September 2022
  • The S Tower construction site, inspection photo 4, 20 September 2022

13 June 2022

21%

  • The S Tower construction site, inspection photo 1, 13 June 2022
  • The S Tower construction site, inspection photo 2, 13 June 2022
  • The S Tower construction site, inspection photo 3, 13 June 2022
  • The S Tower construction site, inspection photo 4, 13 June 2022

All 84 site photos, by inspection date

Context

Site A has 3 projects under construction, 51% built on average.

Sobha has 27 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The S Tower?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The S Tower handover date?
Construction of The S Tower is recorded as complete, with a registered completion date of June 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The S Tower?
The S Tower was 100% built at the site inspection on 20 May 2025. The site has been inspected 8 times since June 2022. The Land Department took 84 site photos at its inspections.
Is The S Tower delayed?
The register lists construction as complete.
Who is building The S Tower?
The registered developer is Sobha. It has 27 other projects under construction in Dubai.
Which bank holds the escrow account for The S Tower?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.