Damac Casa construction progress
Damac Casa in Site A is 34% built at the Land Department inspection of August 2026. Developer Aqua Viridis Investment.
34%
Built, at the Land Department site inspection of 18 August 2026
- Finish at recent pace
- August 2029
- Construction started
- December 2023
- Registered with the Land Department
- October 2023
- Developer
- Aqua Viridis Investment
- Community
- Site A
- Units
- 405
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- داماك كازا
- Land Department project number
- 2801
- Land Department site inspections
- 8
Schedule
Since August 2025 Damac Casa has added about 1.8 points a month. At that rate the site reaches 100% around August 2029. The Land Department has no completion date on record to compare it with.
Site inspections
18 August 2026
34%+7.7 pts
21 April 2026
26%+6.4 pts
22 December 2025
19%+7.7 pts
20 August 2025
12%+4.4 pts
10 April 2025
7.3%+3.5 pts
27 December 2024
3.9%+3.8 pts
20 May 2024
0.1%+0.1 pts
28 September 2023
0%
Context
Site A has 3 projects under construction, 51% built on average.
Own a unit in Damac Casa?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Damac Casa be completed?
- The Land Department has no completion date on record for Damac Casa yet.
- How much of Damac Casa is built?
- 34%, measured at the Land Department site inspection on 18 August 2026. The Land Department engineers have inspected the site 8 times since September 2023.
- Who is building Damac Casa?
- The registered developer is Aqua Viridis Investment.
- Which bank holds the escrow account for Damac Casa?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)








.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)










.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)